In the bar chart method, works are first split into activities. These activities are then listed in the order of construction priorities, generally on the left hand side column, while the time scale is plotted horizontally on the top and/or bottom of the chart. The bar against each activity represents its schedule of work. The start of the bar marks the commencement of the activity and the end of the bar, its completion. The length of the bar on the calendar scale represents the duration of the activity data and the rectangular shape bar represents the activity schedule.
The time base of bar charts-and, for that matter, all scheduling techniques is the project calendar. Generally, this calendar covers a bar or tabulated format, a project’s life span from the date it started to the date of its final completion. It specifies the dates when the activities can be scheduled for execution. It shows all calendar months, weeks, working days, weekend non-working days and holidays. The calendar weeks may have the standard five or six working days. The detailed calendar also highlights the various non-working days such as the weekends and national and other holidays. The project calendar and its parts are invariably, represented in a bar format.
The chart can be vertically divided into three divisions. The left division group activities are listed in the sequence of their execution. The central portion contains the data of activities. The right division depicts the calendar and the schedule of activities. Graphically, the three vertical segments of a bar chart can be arranged in the following ways:

a.     Activity description, data and calendar. This is commonly adopted sequence.

b.     Activity description and calendar. This is used where data is omitted.


c.     Calendar with activity (or work package or task) only with description written inside or at the end of the bar. It is particularly useful for making a schedule for a large project.

d.     Data followed by calendar with description inside or at the end of the bar. This facilitates scheduling of long duration projects.

Bar charts are easy to plot, comprehend and communicate, and are most appropriate for presentation of schedules. However, as planning technique, the bar chart is not suitable for complex projects due to the following reasons:

a.     It does not reflect the relationship between various activities which are common feature of all complex projects.

b.   It cannot identify and highlight the emerging critical tasks needing special attention for preventing schedule slippages, time overruns, and other bottlenecks.


c.      In complex projects, time durations are often educated guesses. Any change in schedule or time duration would require a redrawing of the multi-task bar chart schedule.

Thus, it can be said that the bar chart format is most useful for presentation of schedules, but as a planning technique, it is not suitable for scheduling of complex projects.