Estimating cost of
construction methods
An accurate reliable
estimate or forecast of the probable cost of construction of any building or
civil engineering work can only be found out after planning, designing and
preparation of detailed drawings. The process will involve working out and
pricing detailed quantities for each item of work like excavation, concrete,
brickwork etc., applying current market rates and then arriving at the total
cost. This entails considerable effort and expenses, and before undertaking the
same a becomes necessary to assess the likely cost of construction using
approximate methods.
Approximate estimates
may be defined as preliminary forecasts indicating the likely cost of
construction. Approximate estimates are used for :
- making administrative/financial decisions about talking up the work in hand, so that detailed planning can be initiated after getting budgetary approvals,
- assessing commercial viability, i.e. working out probable net returns on investment,
- carrying out building economics/cost planning exercises to decide on the shape/size/construction methods and the like, to be adopted at the time of detailed planning, and for studying aspects like taxation, insurance etc.
Plinth Area or Square
Meter Method
In this method the built-up
area measured at each floor including basement is worked out and added up.
Approximate cost of the proposed building is then worked out by multiplying the
total of plinth area of all floors by construction cost per unit area of a
similar building built in the recent past. The cost per unit area adopted in
the calculation should be suitably modified to cater for the following
variations between the building from which the rate is adopted and the building
for which the approximate estimate is required : difference in ceiling height
and plinth height; difference in type of construction or specifications;
appreciable difference in location; difference in date of construction; change
if any, in the price level of important items or work; and the like.
Cubic Rate or Cubic Meter Method.
This method is based on
the volume of a building in cubic meters, inclusive of hollow spaces inside the
rooms etc. The volume of a building inferred in this method should not be
confused with the volume of solid content of the building like brickwork,
concrete etc. Approximate cost of the proposed building will be volume in cubic
meters of the proposed building multiplied by the cost per cubic meter of
volume of a similar exisiting structure built in the recent past.
For working out volume
of a building in cubic meters, built-up area of the building at each floor
level is multiplied by height of the respective story, except that the height
of ground floor is measured from half the depth of foundations, and height of
top floor in case of pitched roof is measured upto half the height of slanting
portion of the roof. There is however no uniformity of rules for calculating
height of the building, inclusion or exclusion of open narrow ventilating
shafts, roofed over galleries/verandas etc., for the purpose of calculation
volume of the buildings. This diversity of rules will however not make any
difference as long as calculation of volume of the building from which the rate
per cubic meter is derived is done in the same manner as calculation of volume
of the building for which the approximate estimate is to be worked out.
Modifications required
in the rate per cubic meter to allow for variation between the two buildings
being compared will be same as the factors mentioned in the plinth area or
square meter method.
Service Unit Method.
The term 'service unit' relates to the purpose of a building or civil engineering work. Approximate estimates for the following types of buildings/works can be made using the service unit method :
Service Unit Method.
The term 'service unit' relates to the purpose of a building or civil engineering work. Approximate estimates for the following types of buildings/works can be made using the service unit method :
Building/work
|
Service unit
|
Building/work
|
Service unit
|
Building/work
|
Service unit
|
College/school
|
Class room
|
Stable
|
Animal
|
Highway
|
Kilometer
|
Hospital
|
Bed
|
Hotel
|
Room
|
Canal
|
Kilometer
|
Cinema/stadium
|
Seat
|
Hostel
|
Student
|
Water/sewage main
|
Meter
|
Prison
|
Cell
|
Large apartments
|
Tenement
|
Water tank
|
liter
|
The approximate estimate in this method is based on the cost per service unit,
incurred for a building or work constructed in the recent past. Necessary
modification to the unit rate will have to be made to cater for the variations
described in the plinth area or square meter method given above.
Example : Cost of constructing a hostel building to accomodate 100 students
(two per room) including all furniture, toilet blocks, verandah etc. was Rs.
30,20,000. This yeilds a unit rate of Rs. 30,200 per student for similar
hostels.
Typical Bay Method.
Typical bay method for working out approximate estimates is useful for
buildings like row of garages, factory, buildings, railway platforms etc.,
which have several identical bays. A bay is a typical compartment of a
building. For example, a typical bay of a row of garages will be portion of the
building from center to center of two successive columns (or cross walls) in
one direction, and from outer face of front wall upto rear face of rear wall of
the bay in the other direction. The end bay will need to be considered
separately and appropriate adjustment made to cater for gable wall etc. The
approximate estimate will be number of intermediate bays multiplied by cost of
one intermediate bay plus the cost of the two end bays.
Approximate Quantities Method.
In the approximate quantities method all-in-price of each different element or
component of the building is worked accurately as possible as the
first step. For example, (a) all costs involved in the wall per meter
length upto plinth including foundations, damp proof course etc., (b) cost of
wall in superstructure per square meter including brickwork, plastering,
distempering etc., making a prejudged adjustment for openings etc worked out as
a percentage of the measured all area., (c) cost of RCC slab per square meter
inclusive of concrete, reinforcement, centering, formwork, plaster/whitewash
its soffit etc., and all such principle components of the building. The number
of units of each element or component are worked out approximately and
multiplied by the all-in-price per unit. All these costs of the different
elements of the building item added up will give the approximate cost of the
building, after making an allowance for sundry items overlooked.
Empirical Formulae Method.
Approximate method of estimating cost of a building based on empirical formulae
worked out by C.B.R.I. Roorkee labour and material requirements of different
types of buildings. The qunatities materials and labour days multiplied by the
current market rates for the same, yeild the approximate construction cost the
building when added up.
Building Cost Index Method.
The building cost index method of approximately estimating the cost of a
building is suitable for Government departments like CPWD/MES/Railways etc.
whose construction activity continues year after year, and is spread all over
the entry. Average cost of construction of a particular type of building, in
usually the head-quarter region of the department, particular year is worked out.
This worked out cost, for the particular type of building is allotted the index
1 (one), the particular year is treated as the base year. As construction costs
will increase with passage of time, the building index after a passage of say
five years may be 1.25 in relation to the base year for the particular region.
Similarly, as construction costs vary from one region to another. the
construction cost index for a particular region can be worked out relation to
the index of the head-quarter region. Thus the variation in price due to
passage of time as well as regional reference in construction costs can be
monitored, and effectively used for preparing approximate estimates.
Head offices of the various departments receive feed-backs from their zonal or
regional offices intimating the construction actually incurred on recently
completed buildings/projects, and this information is comiled and disseminated
to all informed with preparing approximate estimates for the department.