Concreting under special conditions



Under Water Concreting

When it is necessary to deposit concrete under water, the methods, equipment, materials and proportions of the mix to be used shall be submitted to and approved by the engineer-in-charge before the work is started. In no case shall such concrete be considered as ‘ Design mix concrete '.

The concrete shall contain at least 10 percent more cement than that required for the same mix placed in the dry, the quantity of extra cement varying with conditions of placing. The volume or mass of the coarse aggregate shall be not less than one and a half times, nor more than twice that of the fine aggregate. The materials shall be so proportioned as to produce a concrete having a slump of not less than 100 mm, and not more than 180 mm.

Coffer-dams or forms shall be sufficiently tight to ensure still water if practicable, and in any case to reduce the flow of water to less than 3 m per minute through the space into which concrete is to be deposited. Coffer-dams or forms in still water shall be sufficiently tight to prevent loss of mortar through the walls. Dewatering by pumping shall not be done while concrete is being placed or until 24 hours thereafter.

Concrete shall be deposited continuously until it is brought to the required height. While depositing, the top surface shall be kept as nearly level as possible and the formation of seams avoided. The methods to be used for depositing concrete under water shall be one of the following:

·        Tremie

When concrete is to be deposited under water by means of a tremie, the top section of the tremie shall be a hopper large enough to hold one entire batch of the mix or the entire contents of the transporting bucket if any. The tremie pipe shall be not less than 200 mm in diameter and shall be large enough to allow a free flow of concrete and strong enough to withstand the external pressure of the water in which it is suspended, even if a partial vacuum develops inside the pipe. Preferably, flanged steel pipe of adequate strength for the job should be used. A separate lifting device shall be provided for each tremie pipe with its hopper at the upper end. Unless the lower end of the pipe is equipped with an approved automatic check valve, the upper end of the pipe shall be plugged with a wadding of the gunny sacking or other approved material before delivering the concrete to the tremie pipe through the hopper, so that when the concrete is forced down from the hopper to the pipe, it will force the plug ( and along with it any water in the pipe ) down the pipe and out of the bottom end, thus establishing a continuous stream of concrete. It will be necessary to raise slowly the tremie in order to cause a uniform flow of the concrete, but the tremie shall not be emptied so that water enters the pipe. At all times after the placing of concrete is started and until all the concrete is placed, the lower end of the tremie pipe shall be below the top surface of the plastic concrete. This will cause the concrete to build up from below instead of flowing out over the surface, and thus avoid formation of laitance layers. If the charge in the tremie is lost while depositing, the tremie shall be raised above the concrete surface, and unless sealed by a check valve, it shall be replugged at the top end, as at the beginning, before refilling for depositing concrete.

·        Drop bottom bucket

The top of the bucket shall be covered with a canvas flap. The bottom doors shall open freely downward and outward when tripped. The bucket shall be filled completely and lowered slowly to avoid backwash. The bottom doors shall not be opened until the bucket rests on the surface upon which the concrete is to be deposited and when discharged, shall be withdrawn slowly until well above the concrete.

·        Bags

Bags of at least 0.028 m3 capacity of jute or other coarse cloth shall be filled about two thirds full of concrete, the spare end turned under so that bag is square ended and securely tied. They shall be placed carefully in header and stretcher course so that the whole mass is interlocked. Bags used for this purpose shall be free from deleterious materials.

·        Grouting

A series of round cages made from 50 mm mesh of 6 mm steel and extending over the full height to be concreted shall be prepared and laid vertically over the area to be concreted so that the distance between centers of the cages and also to the faces of the concrete shall not exceed one meter. Stone aggregate of not less than 50 mm nor more than 200 mm size shall be deposited outside the steel cages over the full area and height to be concreted with due care to prevent displacement of the cages.

A stable 1 : 2 cement-sand grout with a water-cement ratio of not less than 0.6 and not more than 0.8 shall be prepared in a mechanical mixer and sent down under pressure (about 0.2 N/mm2) through 38 to 50 mm diameter pipes terminating into steel cages, about 50 mm above the bottom of the concrete. As the grouting proceeds, the pipe shall be raised gradually up to a height of not more than 600 mm above its starting level after which it may be withdrawn and placed into the next cage for further grouting by the same procedure.

After grouting the whole area for a height of about 600 mm, the same operation shall be repeated, if necessary, for the next layer of 600 mm and so on.

The amount of grout to be sent down shall be sufficient to fill all the voids which may be either ascertained or assumed as 55 percent of the volume to be concreted.

To minimize the formation of laitance, great care shall be exercised not to disturb the concrete as far as possible while it is being deposited.

Concrete in Sea-Water

Concrete in sea-water or exposed directly along the sea-coast shall be at least M 15 Grade in the case of plain concrete and M 20 in case of reinforced concrete. The use of slag or pozzolana cement is advantageous under such conditions.

Special attention shall be given to the design of the mix to obtain the densest possible concrete; slag, broken brick, soft limestone, soft sand-stone, or other porous or weak aggregates shall not be used.

As far as possible, preference shall be given to precast members unreinforced, well-cured and hardened, without sharp corners, and having trowel-smooth finished surfaces free from crazing, cracks or other defects; plastering should be avoided.

No construction joints shall be allowed within 600 mm below low water-level or within 600 mm of the upper and lower planes of wave action. Where unusually severe conditions or abrasion are anticipated, such parts of the work shall be protected by bituminous or silico-fluoride coatings or stone facing bedded with bitumen.

In reinforced concrete structures, care shall be taken to protect the reinforcement from exposure to saline atmosphere during storage and fabrication.



Concrete in Aggressive Soils and Water

General

The destructive action of aggressive waters on concrete is progressive. The rate of deterioration which varies with the alkali-resisting property of the cement used, decreases as the concrete is made stronger and more impermeable, and increases as the salt content of the water increases. Where structures are only partially immersed or are in contact with aggressive soils or waters on one side only, evaporation may cause serious concentrations of salts with subsequent deterioration, even where the original salt content of the soil or water is not high.

Drainage

At sites where alkali concentrations are or may become very high, Portland cement concrete is not recommended, and if used, the ground water shall be lowered by drainage so that it will not come into direct contact with the concrete.
Additional protection may be obtained by the use of a chemically resistant stone facing or a layer of plaster of paris covered with suitable fabric, such as jute, thoroughly impregnated with bituminous material.