PROJECT
|
Ref. No.
|
|
|
LOCATION
|
DATE
|
|
Sr. No.
|
DESCRIPTION
|
REMARKS
|
|
|
First coat or second coat
|
|
|
1.
|
Proper & Safe
Scaffolding erected.
|
|
|
2.
|
Base of
the scaffolding is on levelled & compacted ground
|
|
|
3.
|
Proper
bracings provided wherever required.
|
|
|
4.
|
No
scaffolding inserts in the masonary
|
|
|
5.
|
Safety
belts & helmets provided
|
|
|
6.
|
30 Days
for masonary settlement is sattisfied.
|
|
|
7.
|
Katka & chicken mesh
done on the external side
|
|
|
8.
|
R.C.C.surfaces to be
plastered are hacked (tacha) at 1 hack per Sq. Inch & properly
cleaned.
|
|
|
9.
|
The plaster surface is
wetted.
|
|
|
10.
|
Cement slurry sprayed on
concrete surfaces for wetting
|
|
|
11.
|
Farma available for mix
|
|
|
12.
|
Tray available for mortar
mixing
|
|
|
13.
|
Mortar mix proportion(1:4)
for 1st coat & (1:3) for 2nd coat
|
|
|
14.
|
Mix material is used within
30 minutes.
|
|
|
15.
|
RECRON fibres are mixed in
the mix.
|
|
|
16.
|
After 1st coat, Horizontal
brush lines for bonding with next coat.
|
|
|
17.
|
First coat of 12 mm is
checked for line, level, plumb
|
|
|
18.
|
Date of plaster execution
painted on the wall.
|
|
|
19.
|
Second coat of 6 mm is
checked for line, level, and plumb.
|
|
|
20.
|
Date of plaster execution
painted on the wall.
|
|
|
21.
|
Plaster bands are checked
for dimensions, line, level, plumb
|
|
|