SITE PLANNING, DETAILING & EXECUTION PRACTICES


1)     Before starting laying a stone on site, all working drawings must be signed and checked by the PM first and then Sr. Architect / Executive Architect, Chief / Site Engineer, then Chief Architect. This process (of checking and signing) should take less than a week. 

The checking must include scrutiny of:

a) Site plan including levels of plinths, roads, hard paving, soft paving, showing all structures.

b) All engineering drawings.

c) All services and plumbing drawings.

d) Detail landscape drawings.

e) All electrical drawings.

f) Mark all TBM's, swimming pool deck height, final formation level, SWD haunch level, SWD invert level, plinth levels, stilt parking levels, internal roads and pathway levels. 

All temporary structures, i.e. office, crèche, tanks etc should also be on an overlay on this plan.


2)             SETBACKS

a)   Minimum 4 mts. where there is no vehicular access.

b)   6 mts to 7 mts preference with vehicular access.

c)   6 mts turning radius to all the parking places in stilt.

d)   Staircase should connect to parking / open space / pool (not to be blocked by another parking)

e)   Distance between two buildings to be half the mean height.

f)   Ensure all setbacks are maintained as per approved drawings .

g)   Vehicles are to be parked at a discrete distance.


3)             STRUCTURAL COORDINATION:

 Please ensure that all columns and beams are thick enough for RCC steel reinforcement to get the proper specified concrete cover :
i.e.       Pedestals & 
footings                       50 mm
Column                        40 mm
Beams                          30 mm
Slabs                             20 mm
Pardis                           40 mm
            
  All balconies to have a 10 cm drop from the adjoining habitable room floor.


  All sundecks to have a 20 cm drop from the adjoining habitable room floor.