UNITS OF MEASUREMENTS


SL.NO

ITEMS
UNIT
FOR LABOUR WORK
UNIT
FOR COMPLETED ITEM (MATERIAL+LABOUR)
01
Excavation
cum / cft
cum / cft
02
Back filling / soling
cum / cft
cum / cft
03
Footing  (Concreting)
No.
cum / cft
04
P.C.C
sqm / sft
cum / cft
05
Column / Beam / Lintel Concreting
rm / rft
cum / cft
06
Slab concreting
sqm / sft
cum / cft
07
Pardi / Chajja / Loft Concreting
sqm / sft
cum / cft
08
Staircase Concreting
No. (per step)
cum / cft
09
Brick masonry 10cm to 15cm thick
sqm / sft
sqm / sft
10
Brick masonry 23cm thick
sqm / sft
cum / cft
11
Brick masonry 35cm thick
cum / cft
cum / cft
12
U.C.R. masonry
cum / cft
cum / cft
13
Plastering / Pointing
sqm / sft
sqm / sft
14
Flooring / Tiling
sqm / sft
sqm / sft
15
Skirting / Steps
rm / rft
rm / rft
16
Sill Patti
rm / rft
rm / rft
17
Kitchen otta
 No. or rm / rft
rm / rft
18
Painting
sqm / sft
sqm / sft
19
Doors / Windows
 No. or sqm / sft
sqm / sft
20
Plumbing pipes
rm / rft
rm / rft
21
Plumbing fitting / sanitary ware
No.
No.
22
Water tanks
ltr.
ltr.
23
Septic tanks
ltr.
No. of users
24
Road work (asphalting)
sqm / sft
sqm / sft
25
Electrical cabling / Wiring
rm / rft
rm / rft
26
Electrical points
No.
No.
27
Water-proofing to terrace
sqm / sft
sqm / sft
28
Water-proofing of W.C
No.
sqm / sft
29
Gardening (lawn)
sqm / sft
sqm / sft
30
Gardening (trees / bushes)
No.
No.