then volume is 1+1.5+3=5.5 and the total volume
for using mix=1.57 m3 then cement required=1/ 5.5 x 1.57
=0.285m3 x 1440=411 kg. (8+bag)
sand requried=1.5/5.5 x 1.57=0.471 m3
aggregate required=3/5.5 x 1.57=0.853m3
the standard volume of dry mix mortar=1.57..
U can check it in IS code also.
Then volume is
1+1.5+3=5.5 and the total volume for using
mix=1.57 m3 then cement required =1/ 5.5 x 1.57
=0.285 m3 x 1440=411 kg.(8+bag)
sand requried=1.5/5.5 x 1.57=0.471 m3
aggregate required=3/5.5 x 1.57=0.853 m3
the standard volume of dry mix mortar=1.57..