Quality Control
Specific quality control
requirements for the work are indicated throughout the Contract Documents. The
requirements of this section are primarily related to the performance of the
work beyond furnishing of manufactured products.
Quality is constantly
checked by PDCA cycle i.e.,
1. Plan
2. Do
3. Check
4. Action
Quality control involves
incorporating the following:
1.
Formulation & implementation of project specific quality plan
2.
Maintaining records for incoming material inspection
3.
Maintaining records for tests on construction materials
Material list of quality
records
1.
Quality Plan
2.
Documents Control Sheet
3.
Internal & statistical quality control document
4.
Mix design of concrete
5.
Tests reports of bricks, cement, steel, concrete & aggregates
At QC , an Inspection
Testing Plan is received at the foremost .It is then the purchase list of
equipments is prepared according to the ITP and the acceptance of the raw
materials is done.The basic raw materials used at site are listed below
1. Sand
2. Cement
3. Stone Chips
4. Admixture
5. Bricks
6. Adhesive
7. Waterproofing Components
8. Water Sealant
SAND:
In quality control, sand is
checked for zone1, 2, 3 & 4 of which last two are of basic importance.
Zone 2 Sand: Used for
Concreting
Zone 3 Sand: Used for Brick
Masonry Work
· Sieve Analysis
Sieve
analysis determines the gradation or distribution of aggregates particular
sizes within a given sample.
For zone 3
sampling the
percentage passing of sand through 600 micron sieve should be between
60-79.It is checked for silt contents.
There
are two methods of silt check
1. By
Volume Method
2. By
Weight Method
By volume method the silt
content should be between 8% and by weight method it should be between 3%. IS
code: 383-1970 & IS: 2386-1963.
For zone 4
sampling the
percentage passing of sand through 300 micron sieve should be
between 20-65.IS code: 1542-1992
CEMENT :
It is mainly divided in the
following three parts
1. PPC - Portland Pozzolona
Cement
2. OPC - Ordinary Portland
Cement
3. PSC - Portland Slag
Cement
N.B: Initital setting time
of cement should not be less than 30minutes & final setting time should not
be more than 10 hours
Some of the tests performed
in QC for cement are:
1. Consistency
Test
2. Compressive
Test
3. Initial
Setting Time
4. Final
Setting Time
COARSE AGGREGATE:
Stone chips are
coarse aggregate used in concrete mix. Sieve analysis is performed in site
laboratory for stone chips. Stone chips are passed through IS sieves of
perforations 40 mm ,20 mm, 10 mm, 6mm , etc and graded according to the IS code
ref 2386(Part 3) (Procedure) and 383(Actual Criteria).
ADMIXTURE:
IS: 9103-1999 covers the
following types of admixtures
1. Accelerating admixtures
2. Retarding admixtures
3. Water reducing admixture
4. Super plasticizer
admixture and
5. Air entraining
admixtures
BRICKS:
The bricks at site are
divided into two main categories namely
1. Traditional
or Standard Bricks
2. Modular
Bricks
As
per CPWD specifications the size of traditional brick is (230x110x70) mm and
the size of modular brick is (190x90x90) mm.
The
strength of traditional brick is 3 N/mm
· Brick
Testing :
1. Size
& Shape
2. Sharpness
3. Cold
Crushing Strength
4. Water
Absorption
5. Soundness
Concrete:
Concrete
is the homogeneous mixture of Sand, Cement, Coarse aggregate and Water.
Concrete is used to take load in compressive zone.
· Mixing
:
All concrete, whether plain
or reinforced, ordinary or controlled, shall be mixed in a standard type of
concrete mixer not less than two minutes. Materials for concrete shall be
deposited into the drum while it is in rotation. IS code reference for mix
design: 10262-2009
Properties of Concrete that
should be checked at QC are
1. Workability
2. Durability
3. Segregation
4. Bleeding
5. Curing
6. Slump Test
7. Cube test
Workability
The term
workability is used to describe the ease of difficulty with which the concrete
is handled, transported and placed between the forms with minimum loss of
homogeneity.
The
workability, as a physical property of concrete alone irrespective of a
particular type of construction, can be defined as the amount of useful
internal work, necessary to produce full compaction.
If the
concrete mixture is too wet, the coarse aggregates settle at the bottom of
concrete mass and the resulting concrete becomes of non uniform composition.On
the other hand, if the concrete mixture is too dry, it will be difficult to
handle and place it in position. Both these conflicting conditions should be
correlated by proportioning carefully various components of concrete mixture.
The important in correction withworkabilty are as follows:
1) If
more water is added to attain the required degree of workmanship, it results
into concrete of low strength and poor durability.
2) If
the strength of concrete is not be affected ,the degree of workability can be
abstained :
a. by
slightly changing the proportions of fine and coarse aggregates, in case the
concrete mixture is too wet ; and
b. By
adding a small quantity of water cement paste in the proportion of original
mix, in case the concrete mixture is too dry.
3) A concrete
mixture for one week may prove to be too stiff or too wet for another work. For
instance, the stiff concrete mixture will be required in case of vibrated
concrete work while wet concrete mixture will be required for this sections
containing reinforcing bars.
4) The
workability of concrete is affected mainly by water content, water cement ratio
and aggregate-cement ratio.
5) The
workability of concrete is also affected by the grading, shape, texture and
minimum size of the coarse aggregates to be used in the mixture
Durability
The durability of concrete
is defined as its ability to resist weathering action, chemical attack, abrasion
or any other process of deteriorations. Durable concrete will retain its
original form, quality and serviceability when exposed to its environment.
Generally,
constructionindustry needs faster development of strength in concrete so that
the projects can be completed in tirmof before time. The demand is cleared by
high early strength cement, use of very low W/C ratio through the use of
increased cement content and reduced water content.With higher quantity of
cement content, the concrete exhibits greater cracking tendencies because of
increased thermal and drying shrinkage. As the creep coefficient is low in such
concrete, there will not be much scope for relaxation of stresses.Therefore;
high early strength concretes are more prone to cracking than moderate or low
strength concrete.
Field experience have also
corroborated that high early strength concrete are more crack-prone. According
to a recent report, the cracks in pier caps have been attributed to the use of
high cement content in concrete. Contractors apparently though that a higher
than the desired strength would speed up the construction time, and therefore
used high cement content.
Similarly, report submitted
by National Cooperative Highway Research Programme(NCHRP) of USA during 1995 ,
based on their survey ,showed that more than,100000 concrete bridge deck in USA
showed full depth transverse cracks even before structures were less than one
month old.The reasons given are that combination of thermal shrinkage and
drying shrinkage caused most of the cracks.It is to be noted that deck concrete
is made of high strength concrete .These concretes have a high elastic modulus
at an early age.Therefore,they developed high stresses for a given temperature
change or amount of dying shrinkage.The most important point is that such
concrete creeps little to relieve the stresses.
Segregation
Segregation can be defined
as the separation of the constituent materials of concrete. A good concrete is
one in which all the ingredients are properly distributed to make a homo
generous mixture.If a sample of concrete exhibits a tendency for separation of
say ,coarse aggregate from the rest of the ingredients then, that sample is
said to be showing the tendency for segregation. Such concrete is only going to
be weak ; lack of homogeneity is also going to induce al undesirable properties
in the hardened concrete.
Bleeding
Bleeding is sometimes
referred as water gain. It is a particular form of segregation, in which some
of the water from the concrete comes out to the surface of the concrete, being
of the lowest specific gravity among all the ingredients of concrete. Bleeding
is predominantly observed in a highly wet mix, badly proportioned and
insufficiently mixed concrete.
Due to bleeding, water
comes up and accumulates at the surface.Sometimes, along with the water;
certain quantity of cement also comes to the surface. When the surface is
worked up with in the towel and floats, the aggregates goes down and the cement
and water come up to the top surface.
Method of Test
for Bleeding of Concrete
A cylindrical container of
approximately 0.01meter cube capacity, having an inside diameter of 250 mm and
height 280 mm used. A tamping bar similar to the one used for slump test is
used. A pipette for drawing off free water from the surface, a graduated jar of
100 centimeter cube capacity is required for test.
A sample of freshly mixed
concrete is obtained. The concrete is filled in 50 millimeter layer for a depth
of 250±3 millimeter (5 layers) and each layer is tamped by giving stokes, and
the top surface is made smooth by toweling.
The test specimen is
weighed and the weight of the concrete is noted. Knowing the total water
content in 1 meter cube of concrete quantity of water in the cylindrical
container is also calculated.
The cylindrical container
is kept in a level surface free from vibration at a temperature of 27⁰C ± 2⁰C; it is covered with a lid. Water accumulated at
the top is dawn by means of pipette at 10 minutes interval for the first 40
minutes and at 30 minutes interval subsequently till bleeding ceases. To
facilitate collection of bleeding water the container may be slightly titled.
All the bleeding water collected in a jar.
Curing
The concrete surfaces are
kept wet for a certain period after placing of concrete so as to promote the
hardening of cement. It consists of a control of temperature and of the
moisture movement from and into the concrete. The term curing of concrete is used
to indicate all such procedures and process.
Period of concrete depend
on the type of cement and nature of work. For ordinary Portland cement, the
curing period is about 7 to 14 days. If rapid hardening cement is used, the
curing period can be considerably reduced.
Following are the purposes
of the curing of concrete:
1. The curing protects the
concrete surfaces from sun and wind
2. The presence of water is
essential to cause the chemical action which accompanies the setting of
concrete.
3. The strength of concrete
gradually increases with age, if curing is efficient.th increase in strength is
sudden and rapid in early stages and it continues slowly for an indefinite
period.
4. By proper curing, the
durability and impermeability of concrete are increased and shrinkage is
reduced.
5. The resistance of
concrete to abrasion is considerably increased by proper curing.
Following are the basic
factors on which the evaporation of water from the concrete surface depends:
1. Air temperature
2. Fresh Concrete temperature
3. Relative humidity; and
4. Wind velocity
Slump Test
Slum test is the most
commonly used method of measuring consistency of concrete which can be employed
either in laboratory or at site of work. The apparatus for conducting the slump
test essentially consists of a metallic mould in the form of a frustum of a
cone having the internal dimensions as under:
Bottom
Diameter : 20 cm
Top
diameter : 10
cm
Height : 30
cm
For tamping the concrete, a
steel tamping rod 16 mm die, 0.6 meter along with bullet and is used. The mould
is placed on a smooth,horizontal,rigid and non – absorbant surface.The mould is
then filled in four layers,each approximates ¼ of the height of the mould.Each
layer tamped 25 times by the tamping rod taking care to distribute the strokes
evenly over the cross section.After the top layer has been rodded,the concrete
is stuck off level with a trowel and tamping rod.The mould is removed from the
concrete immediately by raising it slowly and carefully in a vertical
direction.This allows the concrete to subside.Th subsidence is referred as
SLUMP of concrete.The difference in level between the height of the mould and
that of the highest point of the subsided concrete is measured. The difference
in height in mm .is taken as Slump of Concrete.