Give
the meaning and situations where following payments are made to contractor.
First and final payment
Advance payment
Ans.
First
and final payment
The term indicates a single
payment, made for a job or contract on its completion. In this case the payments
is finished by one payment after the completion of the work. This is usually
application for small work.
Advance
payment
This means payment made on a
running account to a contractor for work done by him but not measured. Advance
payment is not generally made to the contractor but may be made under special
cases, when the work is sufficiently progressed but measurement cannot be taken
for certain valid reasons, on the work done, is in no case less than the
advance payment made or proposed to be made and detailed measurement will be
taken as soon as possible.
Give
the meaning of lumpsum contract and state four advantages and four
disadvantages of it.
Ans.
Lumpsump
contract
In lumpsump contract, the
contractor undertakes the execution of construction of a specific work and
shown in the drawings and described by specifications. The contractor will
complete the work within the stipulated time for a fixed amount. There are no
individual rates quoated, thus it becomes difficult to make adjustments in the
contract value of any changes one makes in work out later stage.
In lumpsum contract, generally
the lumpsum value is paid to the contractor on the completion of the work. On
completion of the work no detailed measurement of different items of the work
is required but the whole work is compared and checked with plans and drawings.
Advantages
From
the tender of the work, the owner can visualise the approximate cost of the
work.
The
owner need not require to keep staff for keeping any account.
Only an
engineer, on behalf of the owner to required to see that the work is being
carried out as per drawing and specifications.
The
contractor can gain more benefits by excellent planning and by effective
management on the site of the work.
Disadvantages
All the
details of the work are not specified in the content document.
In case
of additional work is to be done on the job, the contractor claims more rates
for the items not included in the agreement.
Before
the contract is set out, the project has to be studies thoroughly and is
prepare all the content documents in every respect. This is a time consuming
work and is costly.
Give
the meaning and purpose of the following
Administrative approval
Technical sanction
Ans.
Administrative
approval
For any work or project
required by a department, an approval or sanction of the competent authority of
the department, with respect to the cost and the work is necessary at the first
instance. The approval authorises the engineering department to take up the
work. Administrative approval denotes the formal acceptance by the department
concerned of the proposal, and after the administrative approval is given, the
engineering department (pwd) takes up the work and prepares detailed designs,
plans and estimates and then execute, the work. The engineering department
prepares approximate estimates and preliminary plans and submits to the
department concerned for administrative approval.
Technical
sanction
Technical sanction means the sanction
if the detailed estimate, design calculations quantities of works, rates and
costs of the work by the competent authority of the engineering department.
After the technical sanction of the estimate given, then only the work is taken
up for construction. In case of original work, the counter signature of the
local head of the department should be obtained in the plan and estimate before
technical sanction is accorded by the engineering department, the power of the
technical sanction, delegated to various govt. officials in the order shown
below –
The
chief engg. – full powers
The
superintending engr. – san. Up to 15 lakhs
The
executive engr. – san. Up to 3 lakhs.
Give
the meaning of the following terms.
Labour
contract
Security
deposit
Defect
liability period
Liquidated
damage
Ans.
Labour
contract
In labour contract, the
contractor undertakes contract for labour portion only. All materials for the
construction, are arranged and supplied at the site of the work by the
department or owner, the labour contractor engages the labour and gets the work
done according to the specifications.
Security
deposit
On acceptance of the tender the
contractor has to deposit 10% of the tendered amount as security deposit with
the department which is inclusive of the earning money already deposited. This
amount is kept as a check so the contract fulfils all the terms and conditions
of the contract and carries out the work satisfactorily according to the
specifications and maintenance the progress and completes in time. If the
contractor fails to fulfil the terms of contract his whole or part of the
security deposit is forfeled by the government. The security deposit is
returned to contractor after the satisfactory completion of the whole work.
Defect
liability period
After completing the work or project by the
contractor some period is fixed in the contract, to see for any defects in the
work due to materials or workmanship not in accordance with content. This is
know as defect liability period. Defect liability period is generally adopted
as the period covering the first monsoon, usually specified as six months after
the virtual completion. If mothing is mentioned about the same in the contract,
then the defect liability period is taken as 12 months from the date of virtual
completion.
Contractor’s liability, for the
defects ceases on the issue of the final certificate. Improper works executed
due to defective workmanship or materials are to be removed and re-executed at
the contractor’s cost in time.
Liquidated
damages
It is a fixed stipulated sum of
penalty payable by the contractor having no relationship with the real damage.
Is is normally exhorbitant and fixed per day, varying from Rs. 50 to Rs. 100 /-
per day for the excess period taken for the completion of the work than that
specified in the contract.
Give
the list of documents included in the tender set.
Ans.
List
of the documents in the tender set
Prescribed
form of tender
Conditions
of contract
Contract
documents
Scheduled
of quantities
Detailed
drawings
Detailed
specifications
Give
the list of information given in the tender notice.
Ans.
List
of information given in the tender notice
Mode of
submitting tender
Name of
the authorities inviting tenders
Nature
of the work and its location
Estimated
cost
Time
limit for completion
The
date, time and place of receipt and opening of tenders.
Availability
of forms – place, time and cost of forms
Amount
of Earnest Money
Amount
of Security deposit
Reservation
of right to reject bids
Validity
of tender
Define
tender and state only tender notice is given in the news papers.
Ans.
Tender
Tender is an offer inwritting
to execute some specified works or to supply materials at certain rates, within
a fixed time, under certain conditions of contract and agreement between the
contractor and the department or owner. Sealed tenders are invited and the work
is allotted to the lowest tenderer. While inviting tenders the bill or
quantities, detailed specifications, conditions of contract and complete
drawings are supplied on payment the contractors who wants to tender or quote
their rates.
Wide publicity for a tender is
given to secure the benefit of keen completion amongst a considerable number of
firms/contractors and potential bidders for big and specialised job or design
and manufacture, even globel tenders are sometimes invited by the authority to
get competitive offers from various specialised firms or reputed manufacturers
throughout the world. News papers, journals and leading magezines etc. are the
best means of giving wide publicity.
What
care you as contractor will take while submitting a tender.
Ans.
Precautions
while submitting tenders
Nature
of the job or work is studied in detail to assures executions of the job and
availability of materials.
Schedule
of rates one referred for estimating the cost of the work.
All the
relevant details are filled, clearly written without overwriting or changing
the figures.
All the
documents, supplied with the tender are submitted before due time.
The
amount or the rate column in the tender is filled in after assessing the
competition involved in the tender.