STEEL MATERIALS:
·                     Allowable wastage for steel works is 3 %( i.e. cutting/bending wastage).
·                     For reconciliation purpose, + or -2% allowable for rolling margin in this accounts.
·                     Above 25 mm dia of rods 5% wastage should be considered.
CONCRETE MATERIALS:
·                     Concrete pouring or placing time & during loading, transportation lot of concrete it will be waste.So normally concrete wastage 3% considered.  
TILES MATERIALS:
·                     Tiles loading,transportation and placing time lot of broken and cutting it will be happened.
·                     Tiles wastage normally 5% Considered.
PAINT MATERIALS:
·                     Paints applying at the time some paints it will fall on the ground.so during time wastage it will be happen.
·                     Paints wastage normally 2% Considered.
GRANITE MATERIALS:
·                     Granite materials loading,transportation and placing time lot of broken and cutting it will be happened.
·                     Granite wastage normally 5% to 8% will be Considered.
BRICKS MATERIALS:
·                     Bricks materials loading,transportation and placing time lot of broken and cutting it will be happened.
·                     Bricks wastage normally 5% will be Considered.
CEMENT MATERIALS:
·                     Cement materials loading,transportation ,mixing ,shifting & placing time  lot of wastage it will be happened.
·                     Cement materials wastage normally 1.5%  to 2% will be Considered.
COARSE AGGREGATE MATERIALS:
·                     Coarse aggregate materials loading,transportation and placing time lot of wastage it will be happened.
·                     Coarse aggregate materials wastage normally 5% will be Considered,
FINE AGGREGATE MATERIALS:
·                     Fine aggregate materials loading,transportation and placing time lot of wastage it will be happened.
·                     Fine aggregate materials wastage normally 10% will be Considered
STRUCTURAL STEEL MATERIALS:
·                     Structural steel materials fabrication time  lot of cutting and wastage it will be happened.
·                     Structural steel materials wastage normally 5 to 10% will be Considered
As Per Study  done at different Locations Considering different atmospheric conditions,the average wastage of materials are.
·                     Cement = 1.3%
·                     Reinforcement Steel =3.35%
·                     Brick =4.42%
·                     Course Aggregate = 4.49%
·                     Sand = 3.56 %