How to calculate internal plaster quantity?




12mm thick internal plaster

Considering 100sqm area

Proportion of C:M = 1:4

Summation of proportion =5

Quantity of one cement bag = 0.035cum

Quantity of wet mortar = 0.012 x 100 = 1.2cum

Adding 15% wastage = 1.2 + (1.2 x 0.15) =1.38cum

Volume of dry mix = 1.38 + (1.38 x 1/3) =1.84cum

Volume of cement = (dry volume / 5) x 1
                              = (1.84 /5) x 1
                              = 0.368cum
                              = 0.368 / 0.035
                              =10.5 bags

Volume of sand = (dry volume / 5) x 4
                          = (1.84 /5) x 4
                          = 1.472 cum




MATERIALS
QUANTITY
RATE (RS)
AMOUNT (RS)
Sand
1.472cum
1300 /cum
1913
Cement
10.5bags
250 / bag
2625
Scaffolding
L.S
550
550



LABOURS
QUANTITY
RATE (RS)
AMOUNT (RS)
Mason
8nos
200
1600
Helper
12nos
90
1080
Total
7768


 Tools & Plants
1%
0f total
   77.68


Total
7845.68
 Water charges
2%
Of total
      156.91


Total
8002.59
 Supervisor, Overhead & Profit
25%
Of the total
2000.65


Total
10003.23

RATE FOR 100m² = 10003.23Rs.
RATE FOR 1m²     = 100.03Rs.