12mm thick internal plaster
Considering 100sqm area
Proportion of C:M = 1:4
Summation of proportion =5
Quantity of one cement bag = 0.035cum
Quantity of wet mortar = 0.012 x 100 = 1.2cum
Adding 15% wastage = 1.2 + (1.2 x 0.15) =1.38cum
Volume of dry mix = 1.38 + (1.38 x 1/3) =1.84cum
Volume of cement = (dry volume / 5) x 1
= (1.84 /5) x 1
= 0.368cum
= 0.368 / 0.035
=10.5 bags
Volume of sand = (dry volume / 5) x 4
= (1.84 /5) x 4
= 1.472 cum
MATERIALS
|
QUANTITY
|
RATE (RS)
|
AMOUNT (RS)
|
Sand
|
1.472cum
|
1300 /cum
|
1913
|
Cement
|
10.5bags
|
250 / bag
|
2625
|
Scaffolding
|
L.S
|
550
|
550
|
LABOURS
|
QUANTITY
|
RATE (RS)
|
AMOUNT (RS)
|
Mason
|
8nos
|
200
|
1600
|
Helper
|
12nos
|
90
|
1080
|
Total
|
7768
|
Tools & Plants
|
1%
|
0f total
|
77.68
|
Total
|
7845.68
| ||
Water charges
|
2%
|
Of total
|
156.91
|
Total
|
8002.59
| ||
Supervisor, Overhead & Profit
|
25%
|
Of the total
|
2000.65
|
Total
|
10003.23
|
RATE FOR 100m² = 10003.23Rs.
RATE FOR 1m² = 100.03Rs.