The project work-breakdown process
involves breaking down of the project work into manageable parts arranged in a
hierarchical order till the desired level is reached. The work-breakdown levels
are broadly categorized into five levels. These levels, arranged in a
descending hierarchical order are given here
Sub-project level
Task level
Work-package level
Activity level
Operations level
Each level has certain features
associated with it. However, it may be noted that level categorization is a broad
concept and at times their overlapping may become unavoidable.
Work breakdown of the 2000 Housing
Units Project is outlined in fig. The project work included construction of
2000 residential apartments, educational buildings, public buildings, a civic centre,
connected external utility services and landscaping. The total value of
contracted works was approximately US $160 million and the project was
contracted for completion in 36 months. This project scope of work is described
in fig.
The work-breakdown structure of a
project forms the basis for listing of activities, modification of systems,
sorting data by hierarchy levels, structuring of work organization and managing
similar-scope multi-projects.
Sub-projects Level
Sub-projects are derived by dividing
the project work into independent large-volume mini projects or task groups.
For instance, in a housing project, each group of major works which can
progress in a systematic manner, without interference from other works can be
termed as a sub-project.
The number of sub-projects in a
project varies with the nature of the project. Each sub-project comprises one
or more substantial work tasks. The sub-project level aids in identifying
tasks. In the 2000 Housing Units
Project, each type of residential,
educational and public building can be taken as a sub-project.
Typical Housing Project
Work-breakdown Levels Salient Features Generally Associated with Levels
SI. NO.
|
Features
|
Sub-project
|
Task
|
Work Package
|
Activity
|
Operations
|
1.
|
Level designation
|
Level 1
|
Level 2
|
Level 3
|
Level 4
|
Level 5
|
2.
|
Work-breakdown hierarchy
|
Project to sub-project
|
Sub-project to tasks, project to
tasks (directly)
|
Tasks to work packages
|
Work packages to activities
|
Activities to operations
|
3.
|
Management responsibility
|
Project team
|
Task-responsibility unit
|
Work centers
|
Work centers
|
Site foreman
|
4.
|
Planning level
|
Corporate plan
|
Project-summary plan, Design
preparation plan,Contract-finalsiastion plan
|
Project master plan
Constructed works mile-stone plan,
Project budget
|
Project detailed plan
Contracted works-control plan,
Task/work package plan.
Short-term work programmes,
Resources mobilisation plan
|
Foreman-work programmes
|
5.
|
Plan
Duration unit
|
Months
|
Months/weeks
|
Weeks
|
Weeks/days
|
Days/hours
|
6.
|
Project control basis
|
Corporate control
|
Management control
|
Cost control
|
Time control, Productivity
control, Sales control
|
Productivity control
|
7.
|
Work inter-dependency with other
jobs
|
Independent, can proceed without
interference
|
Generally independent
|
Mostly inter-dependence
|
Interdependent
|
Interdependent
|
Tasks Level
The project or sub-project work can
be split up into various tasks. A task is an identifiable and deliverable major
work. It is an entity in itself and can be performed without much interference
from other tasks. A task is supported by its design package. Each task is
assigned time and cost objectives and is provided with planned resources for
accomplishing the task objectives. The task execution is entrusted to a task
responsibility unit, headed by a manager or a senior engineer.
Task level is used in the project-summary
plan, the design-preparation plan and the contract tendering plan. In the 2000
Housing Units Project, the construction works in each residential building can
be grouped under three main tasks, i.e. foundation, superstructure and
finishes.
Work-packages Level
A project task can be further
subdivided into one or more work packages. Each work package contains a
sizeable, identifiable, measurable, costable and controllable package of work.
Fig. shows the work packages for the construction of a residential building of
the Housing Unit Project.
In the project master plan or the
contracted works-control plan, each work package is assigned its performance
objectives. These are generally stated in terms of its completion period,
standard cost, resource-productivity standards and the standard sale price. The
measure of performance thus, gets closely linked with the execution of its work
packages.
Work packages form a common base for
linking the key functions in project management. The work-package concept leads
to the simple-management theory of managing, designing, estimating, planning,
organizing, directing, communicating and controlling, using these work packages
as the base lines. In the 2000 Housing Units Project, foundation work of a
residential building can be broken down into four work packages-base, raft,
plinth wall, ground floor slab.
Activity Level
A work package can further be broken
down into various identifiable jobs, operations and processes, which consume
time and possibly, other resources and are necessary for its completion. Each
one of this is called an activity. As an example, the various activities
involved in the construction of foundation of residential building are listed
in fig.
The breaking down of a work package
into its constituent activities requires a study of the methodology of
execution of the work package. This methodology, generally known by the term
method statement, is evolved by the concerned planning engineer using his
construction experience and through his discussions with the respective project
engineers.
Operations Level
An activity comprises one or more
operations. Each operation contains a part of the work content of the activity.
It generally has particular type or a fixed group of resources associated with
it. It is performed during the scheduled time duration of the activity. Some
operations may start with the commencement of the activity, while others may
take place during its time duration. In some situations, performance periods of
operations may overlap.
Operations are not considered during
the network modeling and analysis stage except that the sum of the costs of
operations equals the activity cost. They form the basis for allocation and
scheduling of resources of each activity. In the 2000 Housing Units Project
operation involved in activity ‘concreting raft’ of foundation work include
·
Cleaning and preparing inner side of
the raft for concreting
·
Pumping concrete
·
Spreading and vibrating concrete
·
Finishing of top concrete surface
The construction
projects are best controlled by the work packages, and best programmed for day
work by using operational level best planned and monitored by the activities. A
project planner uses activity as the common data base for project planning. The
activity duration forms the basis for time planning and scheduling of project
work. Detailed information about resources such as men, materials and machinery
needed for execution of each activity enables the preparation of resource
forecasts. The activity sale price is used to determine the income and
cash-flow forecasts. The activity base is vital for monitoring the progress of
the project work. In the 2000 Housing Units Project foundation construction
task can be broken down into 27 activities shown in fig.