Calculations Of Shuttering Material Requirement By Quick Method Estimation For 232 sqm (2500 sft) Of Slab Area






SR. NO.
MATERIAL REQUIRED
UNIT
MULTIPLYING CONSTANT BY THUMB RULE
APPROXIMATE QUANTITY OF MATERIAL REQUIRED
1
Plywood 12 mm thick of size 2.44 m X 1.22 m (8’0”X4’0”)
2500 sft
0.02
50 nos. sheets
232 sqm
0.22
50 nos. sheets
2
Silver oak batten of size 75 mm X 40 mm (3”X1 ½”)
2500 sft
50 sheet of plywood X 65
3250 rft
232 sqm
50 sheet of plywood X 19.82
990 rm
3
Beam bottom planks 40 mm thick (1 ½”)
2500 sft
2500 sft X 0.24
600 rft
232 sqm
232 sqm X 0.79
183 rm
4
Wooden props
a) For beam
2500 sft
600 rft beam bottom X 0.5
300 Nos.
232 sqm
183 rm beam bottom X 0.5
300 Nos.
b) For slab
2500 sft
2500 sft X 0.16
400 Nos.
232 sqm
232 sqm X 1.72
400 Nos.
5
Wooden batten for supporting slab plates
75 mm X 75 mm (3”X3”)
2500 sft
2500 X 0.4
1000 rft
232 sqm
232 X 1.31
305 rm
6
Steel plates of size 60 cm X 90 cm (2’0” X 3’0”)
2500 sft
2500 X 0.16
400 Nos.
232 sqm
236 X 1.72
400 Nos.
7
Wire nails
2500 sft
2500 X 0.020
50 kg
232 sqm
232 X 0.22
50 kg
8
Shuttering oil
2500 sft
2500 X 0.006
15 liters
232 sqm
232 X 0.065
15 liters
9
M.S. clamps (shikanja)
2500 sft
2500 X 0.08
200 Nos.
232 sqm
232 X 0.86
200 Nos.