INTERNAL PLASTER
Surface Preparation :
- Chipping of bulged concrete to bring it in one level.
- Hacking and/or applying hack-aid over concrete surface.
- Level gauge patches @ 1.5 M to 1.60 M interval (Horizontally & Vertically) To be checked with plumb bob, string tied diagonally vertically and right angle wherever applicable.
- Completion of concealed electrical conduits and plumbing lines.
One coat Plaster :
- Mortar should be mixed in mixer only.
- Plastering done with aluminum level Patti with respect to level gauge patches.
- After 30 min. neeru applied with blade.
- Leakages if any (toilet/w.c.) attended.
- Window sills jamb and/or subframe should be completed.
- Vertically of window/door frames.
- Watering (Tarai) is done one day before.
- To check that the thickness of plaster for ceiling should not exceed specified thickness i.e. 12 mm.
- Availability of Farmas for mixing of mortar.
- Concrete nails to door hold fasts on cool side.
- Fixing chicken mesh at RCC/masonry joints/concealed electrical conduit.
- Availability of mortar trays (optional).
- Changes (Alterations) if any completed.
- Fans hooks on ceiling in position.
- Junctions boxes temporarily sealed.
- Whether floor is clean before plaster and after plaster work.
- To check quantity of cement mortar.