• The pictorial representation of activities and events of project is called Network.

  • An activity needs time and resources.

  • Milestone charts were developed around Periodical estimation of resource treasure.

  • PERT stands for Programme Evaluation and Review Technique.

  • CPM (critical path method) adopts Deterministic approach.

  • The thickness of a 25 gauge sheet is generally less than 1 mm.

  • The standard width of asbestos cement corrugated sheet is 1.05 m.

  • Vertical iron columns required to support the beams and to carry the load of the structures above and to transfer the load to the foundation are called steel stanchions.

  • The useful area or liveable area of a building is called carpet area.

  • When canal is fully in blanking, a wall of puddle clay is provided in the centre of the banks to prevent loss of water by seepage. This wall is called core wall.

  • Workmen’s compensation: insurance, etc. are part of the overhead expenditure in a construction project.

  • Travelling expenses form part of the general overhead expense.

  • For any steel pipe work estimates all the dimensions like length, gauge, diameter and type of steel are important considerations.

  • Brackets are usually measured in terms of weight in kg.

  • During estimation the flat surface area of sheet is increased by 15 %, whenever white washing and distempering is done on corrugated iron sheets.

  • Preparatory work for painting involves cleaning, removing, rubbing down and burning.

  • To account for area of a flush door the flat area is multiplied by 1.

  • Estimate for electrical wiring is prepared on the basis of points.

  • Sales Tax is generally not applicable to residential buildings.

  • The value of a property which can be obtained at any particular time from the open market. When put for sale, is called its market value.

  • The probability factor Z in PERT is given by the formula (Scheduled time-earliest expected time)/(Standard deviation).

  • The total float for any activity along the critical path in CPM is Zero.

  • Cost slope of the direct cost curve is given by (Crash cost-normal cost)/(Normal time – crash time).

  • Net rent + outgoing = Gross rent.

  • The thickness of wall for a building depends on its height, load and length.