SCHEDULE OF OPENINGS

SR. NO.
ITEM
DIAMENSION’S
D
DOOR
1.20 M X 2.10 M
D1
DOOR      
0.90 M X 2.10 M
D2
DOOR
0.75 M X 2.10 M
W
WINDOW
1.20 M X 1.20 M
V
VENTILATION
0.75 M X 0.90 M
V1
VENTILATION
1.20 M X 1.20 M


Brick wall quantity

Store room ( 2.20 meter x 3.00 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam,window or door or ventilator)

= (2.20 x 2 + 3.00 x 2) x 3 meter – W – W – D1 – B1 – B10 – B3 – B17
= 31.2 – (1.20 x 1.20) – (1.20 x 1.20) – (0.90 x 2.10) – (600) – (650) – (600) – (500)
= 31.2 – 1.44 – 1.44 – 1.89 – 0.6 – 0.65 – 0.6 – 0.5
= 24.08 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 24.08 x (30/100)……..(converting thk into meter)
Volume of brick wall = 7.224 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 7.224 / 0.002
Total no. of bricks required = 3612 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 7.224 – (0.001539 x 3612)
Volume of mortar required = 1.66 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.665 / 1+6
Quantity of cement required = 1.665 / 7
Quantity of cement required = 0.23 m3 …….(cubic meter)

1 m3 = 30 bags
0.23 m3 = ?

Therefore, cement required in bags = 0.23 x 30 = 6.9 bags say 7 bags

Quantity of sand required
= 0.23 x 6
= 1.38 m3 …..(cubic meter)


Brick wall quantity

kitchen room ( 2.50 meter x 3.00 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam,window or door or ventilator)

= (2.50 x 2 + 3.00 x 2) x 3 meter – W – D1 – B1 – B3 – B12
= 24 – (1.20 x 1.20) – (0.90 x 2.10) – (600) – (600) – (650)
= 24 – 1.44 – 1.89 – 0.6 – 0.6 – 0.65
= 18.82 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 18.82 x (30/100)……..(converting thk into meter)
Volume of brick wall = 5.646 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 5.646 / 0.002
Total no. of bricks required = 2823 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 5.646 – (0.001539 x 2823)
Volume of mortar required = 1.302 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.302 / 1+6
Quantity of cement required = 1.302 / 7
Quantity of cement required = 0.186 m3 …….(cubic meter)

1 m3 = 30 bags
0.186 m3 = ?

Therefore, cement required in bags = 0.186 x 30 = 5.58 bags say 6 bags

Quantity of sand required
= 0.186 x 6
= 1.116 m3 …..(cubic meter)


Brick wall quantity

Verandha (Passage)     ( 5.70 meter x 2.50 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam,window or door or ventilator)

= (5.70 x 2 + 2.50 x 2) x 3 meter – D – D – W – B2 – B4 – B20
= 41.7 – (1.20 x 2.10) – (1.20 x 2.10) – (1.20 x 1.20) – (600) – (700) – (650)
= 41.7 – 2.52 – 2.52 – 1.44 – 0.6 – 0.7 – 0.65
= 33.27 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 33.27 x (30/100)……..(converting thk into meter)
Volume of brick wall = 9.981 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 9.981 / 0.002
Total no. of bricks required = 4990.5 say 4991 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 9.981 – (0.001539 x 4991)
Volume of mortar required = 2.3 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 2.3 / 1+6
Quantity of cement required = 2.3 / 7
Quantity of cement required = 0.328 m3 …….(cubic meter)

1 m3 = 30 bags
0.328 m3 = ?

Therefore, cement required in bags = 0.328 x 30 = 9.84 bags say 10 bags

Quantity of sand required
= 0.328 x 6
= 1.968 m3 …..(cubic meter)


Brick wall quantity

Sitting  room     ( 5.00 meter x 3.60 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (5.00 + 3.60 x 2) x 3 meter – W – W – D2 – D – B10 -  B5 – B13
= 36.6 – (1.20 x 1.20) – (1.20 x 1.20) – (0.75 x 2.10) – (1.20 x 2.10) – (650) – (700) – (650)
= 36.6 – 1.44 – 1.44 – 1.575 – 2.52 – 0.65 – 0.7 - 065
= 27.625 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 27.625 x (30/100)……..(converting thk into meter)
Volume of brick wall = 8.28 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 8.28 / 0.002
Total no. of bricks required = 4140 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 8.28 – (0.001539 x 4140)
Volume of mortar required = 1.91 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.91 / 1+6
Quantity of cement required = 1.91 / 7
Quantity of cement required = 0.272 m3 …….(cubic meter)

1 m3 = 30 bags
0.272 m3 = ?

Therefore, cement required in bags = 0.272 x 30 = 8.16 bags say 9 bags

Quantity of sand required
= 0.272 x 6
= 1.632 m3 …..(cubic meter)


Brick wall quantity

Sitting  room     ( 5.70 meter x 4.10 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (5.70 + 4.10) x 3 meter – W – W – D -  B19 – B6
= 29.4 – (1.20 x 1.20) – (1.20 x 1.20) – (1.20 x 2.10)  – (650) – (700)
= 29.4 – 1.44 – 1.44 – 2.52 – 0.65 – 0.7
= 22.65 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 22.65 x (30/100)……..(converting thk into meter)
Volume of brick wall = 6.795 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 6.795 / 0.002
Total no. of bricks required = 3397.5 say 3398 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 6.795 – (0.001539 x 3398)
Volume of mortar required = 1.566 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.566 / 1+6
Quantity of cement required = 1.566 / 7
Quantity of cement required = 0.223 m3 …….(cubic meter)

1 m3 = 30 bags
0.223 m3 = ?

Therefore, cement required in bags = 0.223 x 30 = 6.69 bags say 7 bags

Quantity of sand required
= 0.223 x 6
= 1.338 m3 …..(cubic meter)


Brick wall quantity

Enterance Hall ( 4.20 meter x 3.00 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (4.20 + 3.00 x 2) x 3 meter – W – W – D -D -  B18 – B9 – B15
= 30.6 – (1.20 x 1.20) – (1.20 x 1.20) – (1.20 x 2.10) - (1.20 x 2.10)  – (650) –(650) -  (700)
= 30.6 – 1.44 – 1.44 – 2.52 – 2.50 - 0.65 – 0.65 - 0.7
= 20.68 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 20.68 x (30/100)……..(converting thk into meter)
Volume of brick wall = 6.204 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 6.204 / 0.002
Total no. of bricks required = 3102 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 6.204 – (0.001539 x 3102)
Volume of mortar required = 1.431 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.431 / 1+6
Quantity of cement required = 1.431 / 7
Quantity of cement required = 0.204 m3 …….(cubic meter)

1 m3 = 30 bags
0.204 m3 = ?

Therefore, cement required in bags = 0.204 x 30 = 6.13 bags say 7 bags

Quantity of sand required
= 0.204 x 6
= 1.224 m3 …..(cubic meter)


Brick wall quantity

Bed room ( 3.60 meter x 5.00 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (2 + 3.60 + 5.00) x 3 meter – W – W – D2 - W -  B8 – B16 – B14
= 31.8 – (1.20 x 1.20) – (1.20 x 1.20) – (0.75 x 2.10) - (1.20 x 1.20)  – (650) –(700) -  (700)
= 31.8 – 1.44 – 1.44 – 1.575 – 1.44 - 0.65 – 0.65 - 0.7
= 23.855 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 23.855 x (30/100)……..(converting thk into meter)
Volume of brick wall = 7.75 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 7.75 / 0.002
Total no. of bricks required = 3875 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 7.75 – (0.001539 x 3875)
Volume of mortar required = 1.79 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 1.79 / 1+6
Quantity of cement required = 1.79 / 7
Quantity of cement required = 0.255 m3 …….(cubic meter)

1 m3 = 30 bags
0.255 m3 = ?

Therefore, cement required in bags = 0.255 x 30 = 7.65 bags say 8 bags

Quantity of sand required
= 0.255 x 6
= 1.53 m3 …..(cubic meter)


Brick wall quantity

Bath room ( 2.60 meter x 1.00 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (2.60 x 2 + 1.00) x 3 meter – V1 – V – D2 – B7 - B11
= 18.6 – (1.20 x 1.20) – (0.75 x 0.90) - (0.75 x 2.10) – (650) – (650)
= 18.6– 1.44 – 0.675 – 1.575 - 0.65 – 0.65
= 13.61 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 13.61 x (30/100)……..(converting thk into meter)
Volume of brick wall = 4.083 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 4.083 / 0.002
Total no. of bricks required = 2041.5 say 2042 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 4.083 – (0.001539 x 2042)
Volume of mortar required = 0.941 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 0.941 / 1+6
Quantity of cement required = 0.941 / 7
Quantity of cement required = 0.134 m3 …….(cubic meter)

1 m3 = 30 bags
0.134 m3 = ?

Therefore, cement required in bags = 0.134 x 30 = 4.02 bags say 5 bags

Quantity of sand required
= 0.134 x 6
= 0.804 m3 …..(cubic meter)


Brick wall quantity

W.C.   ( 1.75 meter x 0.90 meter )

Height of room = 3 meter

Area of wall = (Length of walls x height of wall) – deduction of openings…….(i.e. Beam, window or door or ventilator)

= (0.90 x 2) x 3 meter – V - B11
= 5.4 – (0.75 x 0.90) - (650)
= 5.4 – 0.675 – 0.65
= 4.075 m2  …..(square meter)

Brick wall thickness = 30 cm

Volume of brick wall = Area of wall x height of wall
Volume of brick wall = 4.075  x (30/100)……..(converting thk into meter)
Volume of brick wall = 1.22 m3 ……..(cubic meter)

Actual size of 1 brick with mortar = 20 cm x 10 cm x 10 cm
Actual size of 1 brick with mortar = 0.2 x 0.1 x 0.1
Actual size of 1 brick with mortar = 0.002 m3 ………(cubic meter)

Total no. of bricks required=vol. of brick wall / vol. of 1 brick with mortar
Total no. of bricks required = 1.22 / 0.002
Total no. of bricks required = 611.25 say 612 nos.

Actual size of brick = 19 cm x 9 cm x 9 cm
Actual size of brick = 0.19 x 0.09 x 0.09
Actual size of brick = 0.001539 m3   …..(cubic meter)

Volume of mortar required = Vol. of wall – Vol. of brick
Volume of mortar required = Vol. of wall - (actual size of brick x no.of bricks)
Volume of mortar required = 1.22 – (0.001539 x 612)
Volume of mortar required = 0.279 m3 ….(cubic meter)

Mortar Proportion ( 1:6 )
Quantity of cement required = Vol. of mortar / mortar proportion
Quantity of cement required = 0.279 / 1+6
Quantity of cement required = 0.279 / 7
Quantity of cement required = 0.0398 m3 …….(cubic meter)

1 m3 = 30 bags
0.0398 m3 = ?

Therefore, cement required in bags = 0.0398 x 30 = 1.19 bags say 2 bags

Quantity of sand required
= 0.0398 x 6
= 0.23 m3 …..(cubic meter)