SITE :
|
Shalimar - Anthurium
|
TOWER - 1
| ||||
Sr. No.
|
Activities
|
Duration
|
Start Date
|
Finish Date
| ||
1
|
Excavation in All Soil
|
60 Days
|
01-09-2009
|
31-10-2009
| ||
2
|
Anti Termite Treatment
|
60 Days
|
01-11-2009
|
31-12-2009
| ||
3
|
PCC
| |||||
4
|
RCC & Footings
| |||||
5
|
Stub Columns
| |||||
6
|
For Flat 3 &4 Backfilling
| |||||
7
|
Raft & Raft Beam
| |||||
8
|
Back Filling -II
| |||||
9
|
Soiling & PCC
| |||||
10
|
Completion of Basement Level -2
|
45 Days
|
15-12-2009
|
30-01-2010
| ||
11
|
RCC in Slab & Beam at Basement Level-1
| |||||
12
|
RCC in Slab & Beam at Podium Level-1
|
60 Days
|
01-02-2010
|
31-03-2010
| ||
13
|
RCC in Slab & Beam at Podium Level-2
| |||||
14
|
RCC in Slab & Beam at Podium Level-3
| |||||
15
|
RCC in Slab & Beam at Residential Floor/ Typical Level-1
|
25 Days
|
01-04-2010
|
25-04-2010
| ||
16
|
RCC in Slab & Beam at Residential Floor/ Typical Level-2
|
15 Days
|
25-04-2010
|
05-05-2010
| ||
17
|
RCC in Slab & Beam at Residential Floor/ Typical Level-3
|
15 Days
|
06-05-2010
|
20-05-2010
| ||
18
|
RCC in Slab & Beam at Residential Floor/ Typical Level-4
|
15 Days
|
21-05-2010
|
05-06-2010
| ||
19
|
RCC in Slab & Beam at Residential Floor/ Typical Level-5
|
15 Days
|
06-06-2010
|
25-06-2010
| ||
20
|
RCC in Slab & Beam at Residential Floor/ Typical Level-6
|
15 Days
|
26-06-2010
|
10-07-2010
| ||
21
|
RCC in Slab & Beam at Residential Floor/ Typical Level-7
|
15 Days
|
11-07-2010
|
25-07-2010
| ||
22
|
RCC in Slab & Beam at Residential Floor/ Typical Level-8
|
15 Days
|
26-07-2010
|
10-08-2010
| ||
23
|
RCC in Slab & Beam at Residential Floor/ Typical Level-9
|
15 Days
|
11-08-2010
|
25-08-2010
| ||
24
|
RCC in Slab & Beam at Residential Floor/ Typical Level-10
|
15 Days
|
26-08-2010
|
10-09-2010
| ||
25
|
RCC in Slab & Beam at Residential Floor/ Typical Level-11
|
15 Days
|
11-09-2010
|
25-10-2010
| ||
26
|
RCC in Slab & Beam at Residential Floor/ Typical Level-12
|
15 Days
|
26-10-2010
|
10-11-2010
| ||
27
|
RCC in Slab & Beam at Residential Floor/ Typical Level-13
|
15 Days
|
11-12-2010
|
25-12-2010
| ||
28
|
RCC in Slab & Beam at Residential Floor/ Typical Level-14
|
15 Days
|
26-12-2010
|
10-01-2011
| ||
29
|
RCC in Slab & Beam at Residential Floor/ Typical Level-15
|
15 Days
|
11-01-2011
|
25-01-2011
| ||
30
|
RCC in Slab & Beam at Residential Floor/ Typical Level-16
|
15 Days
|
26-01-2011
|
10-02-2011
| ||
31
|
RCC in Slab & Beam at Residential Floor/ Typical Level-17
|
15 Days
|
11-02-2011
|
25-02-2011
| ||
32
|
RCC in Slab & Beam at Residential Floor/ Typical Level-18
|
15 Days
|
26-02-2011
|
12-03-2011
| ||
33
|
RCC in Slab & Beam at Residential Floor/ Typical Level-19
|
15 Days
|
13-04-2011
|
28-04-2011
| ||
34
|
RCC in Slab & Beam at Residential Floor/ Typical Level-20
|
15 Days
|
29-04-2011
|
14-04-2011
| ||
35
|
RCC in Slab & Beam at Residential Floor/ Typical Level-21
|
15 Days
|
15-04-2011
|
30-04-2011
| ||
36
|
RCC in Slab & Beam at Residential Floor/ Typical Level-22
|
15 Days
|
01-05-2011
|
15-05-2011
| ||
37
|
RCC in Slab & Beam at Residential Floor/ Typical Level-23
|
15 Days
|
16-05-2011
|
31-05-2011
| ||
38
|
RCC in Slab & Beam at Residential Floor/ Typical Level-24
|
15 Days
|
01-06-2011
|
15-06-2011
| ||
39
|
RCC in Slab & Beam at Residential Floor/ Typical Level-25
|
15 Days
|
16-06-2011
|
30-06-2011
| ||
40
|
RCC in Slab & Beam at Residential Floor/ Typical Level-26
|
15 Days
|
01-07-2011
|
15-07-2011
| ||
41
|
RCC in Slab & Beam at Residential Floor/ Typical Level-27
|
15 Days
|
16-07-2011
|
30-07-2011
| ||
42
|
RCC in Slab & Beam at Residential Floor/ Typical Level-28
|
15 Days
|
01-08-2011
|
15/081/2011
| ||
43
|
RCC in Slab & Beam at Residential Floor/ Terrace Level
|
15 Days
|
16-08-2011
|
30-08-2011
| ||
44
|
RCC in OHT, LMR, PARAPET
|
30 Days
|
01-09-2011
|
30-09-2011
| ||
Super Structure Finishes & Services
| ||||||
45
|
Masonry, Plaster & Finishing
| |||||
46
|
Brick/ Block work/ door frames
| |||||
47
|
Laying Conduits in B.Work & fixing of boxes
| |||||
48
|
Internal Plaster & Aluminium Sub frames
| |||||
49
|
POP Punning to Walls
| |||||
50
|
External Plaster to Duct & Service Area
| |||||
51
|
Ext. Wall Plaster
| |||||
52
|
Fixing of Grills & Façade
| |||||
53
|
External Painting
| |||||
54
|
Waterproofing
| |||||
55
|
Terrace Waterproofing
| |||||
56
|
Toilet Waterproofing
| |||||
57
|
IPS to Ducts & Services area etc.
| |||||
58
|
China Mosaic
| |||||
59
|
Tiling/ Flooring & Granite Works
| |||||
60
|
Flooring in Room
| |||||
61
|
Skirting
| |||||
62
|
Kitchen Platform - Cuddapa
| |||||
63
|
Platform Top + Dado
| |||||
64
|
Toilet Flooring
| |||||
65
|
Toilet Dado
| |||||
66
|
Aluminium Windows
| |||||
67
|
Fabricating & Fixing of Aluminium Tracks
| |||||
68
|
Fixing of Aluminium Windows
| |||||
69
|
Fixtures of Aluminium Windows
| |||||
70
|
Carpentry
| |||||
71
|
Fixing of Shutters to Flats
| |||||
72
|
Fix Hardwares to Shutters
| |||||
73
|
Painting
| |||||
74
|
Acralyc Paint
| |||||
75
|
Distemper Paint
| |||||
76
|
Plumbing
| |||||
77
|
Concealed Plumbing
| |||||
78
|
Down Take Lines
| |||||
79
|
Terrace Looping
| |||||
80
|
Install Plumbing/ pneumatic pumps & panels
| |||||
81
|
Fixing Sanitarywares
| |||||
82
|
Fixing C.P. Fittings
| |||||
83
|
Electrification
| |||||
84
|
LT Installation
| |||||
85
|
Wiring
| |||||
86
|
Electrical Fixtures/Switches
| |||||
87
|
Application for Electric NOC
| |||||
88
|
Electrical Inspection & NOC
| |||||
89
|
Electriacal Meters
| |||||
90
|
Comissioning Elec. Supply
| |||||
91
|
Lifts
| |||||
92
|
Delivery of Material
| |||||
93
|
Handing over of shaft
| |||||
94
|
Installation
| |||||
95
|
Testing & Commissioning of Lifts
| |||||
96
|
Lift Certificate
| |||||
97
|
Fire Fighting
| |||||
98
|
Shaft pipe for Wet Riser
| |||||
99
|
Installation of Fire Alaram System
| |||||
100
|
Sprinklers drops at Basement
| |||||
101
|
Sprinklers Heads
| |||||
102
|
Installation of Jocky Pump at Terrace
| |||||
103
|
Install Hydrants, Hose reels
| |||||
104
|
Installation of Fire Pump
| |||||
105
|
Testing & Commissioning of Lifts
| |||||
106
|
C.F.O. Certificate
| |||||
107
|
Solar System (Water Heater)
| |||||
108
|
Delivery of Solar Water Heater Material
| |||||
109
|
Installation of Solar Panels/ Collectors
| |||||
110
|
Piping of OHT to insulated hot water tank
| |||||
111
|
Piping of Pump & Insulated hot water tank
| |||||
112
|
Piping of insulated hot water tank
| |||||
113
|
Testing & Commissioning of Solar System
| |||||
114
|
Common Area Finishing
| |||||
115
|
Lift Lobbies Finishing
| |||||
116
|
Entrance Finishing
| |||||
117
|
Staircase Finishing
| |||||
118
|
Ready for Q.C.
| |||||
119
|
Application for Occupation Certificate
|