SITE :
Shalimar - Anthurium
TOWER - 1
Sr. No.
Activities
Duration
Start Date
Finish Date
1
Excavation in All Soil
60 Days
01-09-2009
31-10-2009
2
Anti Termite Treatment
60 Days
01-11-2009
31-12-2009
3
PCC
4
RCC & Footings
5
Stub Columns
6
For Flat 3 &4 Backfilling
7
Raft & Raft Beam
8
Back Filling -II
9
Soiling & PCC
10
Completion of Basement Level -2
45 Days
15-12-2009
30-01-2010
11
RCC in Slab & Beam at Basement Level-1
12
RCC in Slab & Beam at Podium Level-1
60 Days
01-02-2010
31-03-2010
13
RCC in Slab & Beam at Podium Level-2
14
RCC in Slab & Beam at Podium Level-3
15
RCC in Slab & Beam at Residential Floor/ Typical Level-1
25 Days
01-04-2010
25-04-2010
16
RCC in Slab & Beam at Residential Floor/ Typical Level-2
15 Days
25-04-2010
05-05-2010
17
RCC in Slab & Beam at Residential Floor/ Typical Level-3
15 Days
06-05-2010
20-05-2010
18
RCC in Slab & Beam at Residential Floor/ Typical Level-4
15 Days
21-05-2010
05-06-2010
19
RCC in Slab & Beam at Residential Floor/ Typical Level-5
15 Days
06-06-2010
25-06-2010
20
RCC in Slab & Beam at Residential Floor/ Typical Level-6
15 Days
26-06-2010
10-07-2010
21
RCC in Slab & Beam at Residential Floor/ Typical Level-7
15 Days
11-07-2010
25-07-2010
22
RCC in Slab & Beam at Residential Floor/ Typical Level-8
15 Days
26-07-2010
10-08-2010
23
RCC in Slab & Beam at Residential Floor/ Typical Level-9
15 Days
11-08-2010
25-08-2010
24
RCC in Slab & Beam at Residential Floor/ Typical Level-10
15 Days
26-08-2010
10-09-2010
25
RCC in Slab & Beam at Residential Floor/ Typical Level-11
15 Days
11-09-2010
25-10-2010
26
RCC in Slab & Beam at Residential Floor/ Typical Level-12
15 Days
26-10-2010
10-11-2010
27
RCC in Slab & Beam at Residential Floor/ Typical Level-13
15 Days
11-12-2010
25-12-2010
28
RCC in Slab & Beam at Residential Floor/ Typical Level-14
15 Days
26-12-2010
10-01-2011
29
RCC in Slab & Beam at Residential Floor/ Typical Level-15
15 Days
11-01-2011
25-01-2011
30
RCC in Slab & Beam at Residential Floor/ Typical Level-16
15 Days
26-01-2011
10-02-2011
31
RCC in Slab & Beam at Residential Floor/ Typical Level-17
15 Days
11-02-2011
25-02-2011
32
RCC in Slab & Beam at Residential Floor/ Typical Level-18
15 Days
26-02-2011
12-03-2011
33
RCC in Slab & Beam at Residential Floor/ Typical Level-19
15 Days
13-04-2011
28-04-2011
34
RCC in Slab & Beam at Residential Floor/ Typical Level-20
15 Days
29-04-2011
14-04-2011
35
RCC in Slab & Beam at Residential Floor/ Typical Level-21
15 Days
15-04-2011
30-04-2011
36
RCC in Slab & Beam at Residential Floor/ Typical Level-22
15 Days
01-05-2011
15-05-2011
37
RCC in Slab & Beam at Residential Floor/ Typical Level-23
15 Days
16-05-2011
31-05-2011
38
RCC in Slab & Beam at Residential Floor/ Typical Level-24
15 Days
01-06-2011
15-06-2011
39
RCC in Slab & Beam at Residential Floor/ Typical Level-25
15 Days
16-06-2011
30-06-2011
40
RCC in Slab & Beam at Residential Floor/ Typical Level-26
15 Days
01-07-2011
15-07-2011
41
RCC in Slab & Beam at Residential Floor/ Typical Level-27
15 Days
16-07-2011
30-07-2011
42
RCC in Slab & Beam at Residential Floor/ Typical Level-28
15 Days
01-08-2011
15/081/2011
43
RCC in Slab & Beam at Residential Floor/ Terrace Level
15 Days
16-08-2011
30-08-2011
44
RCC in OHT, LMR, PARAPET
30 Days
01-09-2011
30-09-2011






Super Structure Finishes & Services



45
Masonry, Plaster & Finishing



46
Brick/ Block work/ door frames



47
Laying Conduits in B.Work & fixing of boxes



48
Internal Plaster & Aluminium Sub frames



49
POP Punning to Walls



50
External Plaster to Duct & Service Area



51
Ext. Wall Plaster



52
Fixing of Grills & Façade



53
External Painting



54
Waterproofing



55
Terrace Waterproofing



56
Toilet Waterproofing



57
IPS to Ducts & Services area etc.



58
China Mosaic



59
Tiling/ Flooring & Granite Works



60
Flooring in Room



61
Skirting



62
Kitchen Platform - Cuddapa



63
Platform Top + Dado



64
Toilet Flooring



65
Toilet Dado



66
Aluminium Windows



67
Fabricating & Fixing of Aluminium Tracks



68
Fixing of Aluminium Windows



69
Fixtures of Aluminium Windows



70
Carpentry



71
Fixing of Shutters to Flats



72
Fix Hardwares to Shutters



73
Painting



74
Acralyc Paint



75
Distemper Paint



76
Plumbing



77
Concealed Plumbing



78
Down Take Lines



79
Terrace Looping



80
Install Plumbing/ pneumatic pumps & panels



81
Fixing Sanitarywares



82
Fixing C.P. Fittings



83
Electrification



84
LT Installation



85
Wiring



86
Electrical Fixtures/Switches



87
Application for Electric NOC



88
Electrical Inspection & NOC



89
Electriacal Meters



90
Comissioning Elec. Supply



91
Lifts



92
Delivery of Material



93
Handing over of shaft



94
Installation



95
Testing & Commissioning of Lifts



96
Lift Certificate



97
Fire Fighting



98
Shaft pipe for Wet Riser



99
Installation of Fire Alaram System



100
Sprinklers drops at Basement



101
Sprinklers Heads



102
Installation of Jocky Pump at Terrace



103
Install Hydrants, Hose reels



104
Installation of Fire Pump



105
Testing & Commissioning of Lifts



106
C.F.O. Certificate



107
Solar System (Water Heater)



108
Delivery of Solar Water Heater Material



109
Installation of Solar Panels/ Collectors



110
Piping of OHT to insulated hot water tank



111
Piping of Pump & Insulated hot water tank



112
Piping of insulated hot water tank



113
Testing & Commissioning of Solar System



114
Common Area Finishing



115
Lift Lobbies Finishing



116
Entrance Finishing



117
Staircase Finishing



118
Ready for Q.C.



119
Application for Occupation Certificate