CHECKLIST FOR WBM & ASPHALT ROAD | ||||||||||||||||||||
| 
Sr. No: | ||||||||||||||||||||
| 
SITE : SHALIMAR ANTHURIUM | 
LOCATION : | 
DATE : | ||||||||||||||||||
| 
Ref. Drawing No.   ________________________________________ | ||||||||||||||||||||
| 
Sr. No. | 
Job Description | 
YES | 
NO | 
NA | ||||||||||||||||
| 
1. | 
Check for LAYOUTS, GRADES   & CROSS-SECTIONS OF SUBGRADE prior to spreading of aggregates. | |||||||||||||||||||
| 
2. | 
PREPARATION OF SUBGRADE to   specified Lines and Camber. Check for cleaning and Making up of soft spots   & other irregularities. | |||||||||||||||||||
| 
3. | 
Check for uniform spread   thickness of Aggregates | |||||||||||||||||||
| 
4. | 
Check for DRY ROLLING | |||||||||||||||||||
| 
5. | 
Check for APPLICATION OF   SCREENINGS & BINDING MATERIAL as per specifications. | |||||||||||||||||||
| 
6. | 
Check for SPRINKLING OF WATER   on the aggregates. | |||||||||||||||||||
| 
7. | 
Check for WET ROLLING of   Affregates and COMPACTION. | |||||||||||||||||||
| 
8. | 
Check for FINISHED SURFCES,   COMPACTED THICKNESS. | |||||||||||||||||||
| 
9. | 
CAMBER,LINES AND SLOPE Are   they acceptable ? | |||||||||||||||||||
| 
ASPHALT ROADWORKS | ||||||||||||||||||||
| 
1. | 
Check for LAYOUTS,GRADES   & CROSS=SECTIONS OF SUB-BASE prior to spreading of Aspahlt. | |||||||||||||||||||
| 
2. | 
Check for SURFACE PREPARATION   OF WBM SUB-BASE Check for ceaning and making up of Soft spots & other   irregulaties. | |||||||||||||||||||
| 
3. | 
Is the approved MIX DESIGN   employed for mixing of Premix ? | |||||||||||||||||||
| 
4. | 
Is the Asphalt being laid in   HOT CONDITION ? | |||||||||||||||||||
| 
5. | 
Check for UNIFORM SPREAD   THICKNESS of Premix, is it OK ? | |||||||||||||||||||
| 
6. | 
Check for ROLLING is is   proceeding from edges to centre longtuidinally ? | |||||||||||||||||||
| 
7. | 
Check for FINISHED SURFACES,   COMPACTED THICKNESS,CAMBER, LINES AND SLOPE Are they acceptable ? | |||||||||||||||||||
| 
8. | 
Check for LAYING, ROLLING   & COMPACTION OF SEAL COAT.Is the SURFACE FINISH, CAMBER, SLOPE   satisfactory ? | |||||||||||||||||||
| 
                                                                                             SIGN. OF SITE ENGINEER | ||||||||||||||||||||
| 
CORRECTIVE ACTION PROPOSED | ||||||||||||||||||||
| 
Sign of Project Manager                                                         Sign of Project Manager 