CHECKLIST FOR EXECUTION OF PIPED GAS WORK



1.   MATERIAL AND DESIGN SPECIFICATIONS

a.   The pipes used in the complex should be Mild Steel (ERW-C Class-ISI 1239) Manufactured by Tata / Jindal / Zenith  15mm (1/2") dia. pipe Outer dia. 21.8mm - 21.0 mm minimum, Wall thickness 3.25 mm, Weight of pipe -1.45 kg/m 25 mm (1") dia. Pipe outer dia. 34.2 mm to 33.3 mm minimum, Wall thickness 4.05 mm weight of pipe - 2.97 kg/m

b.  Copper pipes inside kitchen should be manufactured by Hindustan Copper / Nissan Copper. (IS 2501)

c.     All Gas Meters, Gas Regulators, Auto Change Over, First Stage Regulators, Second stage regulators & Ball Valves should be of Comap, (Italy / France Make)

d.  Pigtails (Suraksha Make), Non Return Valve (Gesso Make), Pressure Gauge (Hitec / Dynamic) 

e.     System designed should have uniform pressure in the hot plate in all the flats at all the times, even when all are on at the same time.
          Please ensure weight of pipe for 1m length of pipe. 

2.   CIVIL WORKS 

a. Excavation of trenches Minimum 3ft depth. There should be minimum 1ft difference between the under ground gas pipe and any other service lines ie: (drainage lines, water supply lines, electric cable etc) to avoid any damages to the pipe line, also to avoid crossing. In short under ground gas pipe line should be at the lower most level with respect to service lines.

b.     Compact the excavated trench bed using a Dumas before laying PCC

c.     Lay PCC (1:3:6) at the base of the under ground pipe min 5cms as support base for pipes throughout the length of the trench.

d.     CONTRACTOR TO COMPLETE ITEM C 1 TO C5.

e.  After contractor finishes the above items, multiplast strip of 2mm thickness and as per required width should be fused on entire circumference of the pipes. Put GI wire at every 50cms so that multiplast does not rotate around the pipe.

f.       CONTRACTOR TO COMPLETE ITEM C 7

g.     After contractor finishes the above items encase the pipe with PCC (1:3:6) from all sides minimum 8cms thickness using simple form work to create a box like protection PCC layer. 

h.  Cover soft mud minimum 20cms above the pipe and lay indication/ guidance tiles made of Shahabad / kadappa / broken tiles etc.) and later cover the remaining trench with excavated mud with proper compaction

i.      Drilling of hole in the granite platform in kitchen.

j.      Core cutting wherever required. 



3.   WORKS by the CONTRACTOR

a.   Vertical pipes should be in plumb, properly clamped to wall & painted with one coat anti corrosive paint and two coats of enamel paint (Yellow colour) 

b.     After welding /joining of under ground pipes is completed apply one coat of zinc chromate primer.

c.   Test all under ground and vertical lines with Nitrogen gas at 6 kg/cm2 pressure by closing open ends of by means of valves or dead flanges.

d.   Observe for any leakage at welded joints of pipe, and fittings by bubble test method ie: Make powder soap water (recommended for powder soap used for automatic washing machines). Apply it over the welded pipe joints and fitting joints with help of Brush or cloth soaked in soap water. If there is leakage you will observe bubbles of soap water at the welded area. 

e.     After the leakage test is completed as per satisfaction of Acron Engineer's in charge apply two coats of HB black/ coal tar.


g.   After the multiplast strip fusing is completed wrap the pipe with polythene sheet strips over multiplast. Thickness of polythene sheet should minimum 100 micron or same thickness of polythene as used below PCC for ground floor apartments.