PROJECT
|
Ref. No.
|
|
DRAWING NO.
|
DATE
|
|
LOCATION
|
|
Sr.
|
DESCRIPTION
|
REMARKS
|
No.
|
|
Accepted/rejected with clear reasons
|
1
|
Type of Masonary
|
Laterite,clay/fly ash
brick,concrete block
|
2
|
Masonary width (mm)
|
|
3
|
R.C.C.surfaces touching the
masonary are hacked (tacha) at 1 hack per Sq. Inch & properly
cleaned.
|
|
4
|
Wetting of bricks / stone/
concrete block before laying
|
|
5
|
Farmas available for mortar
proportioning
|
|
6
|
Tray available for mortar
mixing
|
|
7
|
Mortar mix proportion (1:5)
|
|
8
|
Sand is screened
|
|
9
|
Mix material is used within
30 minutes.
|
|
10
|
Proper & Safe
Scaffolding erected.
|
|
11
|
No scaffolding supports to
be inserted in the masonary
|
|
12
|
Masonary Lineout for the
entire floor/room is done with a single coarse of masonary.
|
|
13
|
This laid coarse is checked
for right angles & Dimensions.
|
|
14
|
Per day masonary height
restricted to one meter.
|
|
15
|
R.C.C.(M15) band(100 mm
thick)
|
|
16
|
No vertical joints allowed.
|
|
17
|
Joint thickness between
10-12 mm.
|
|
18
|
Masonary plumb on the side
of which room?
|
|
19
|
Masonary plumb is checked.
|
|
|
|
|
20
|
Cleaning after day's work.
|
|
21
|
Date of masonary execution
painted on the wall.
|
|
22
|
Actual size of openings left
in the masonary.
|
|
CHECKED BY
|
PROJECT ENGINEER
|
||||||||
*
|
Curing is to be carried out
for minimum period of 7 days.
|
||||||||
*
|
Further masonary plaster or
gypsum to be done only after settlement period of 30 days.
|
||||||||
*
|
Katka & chicken mesh
after settlement period.
|
||||||||