CHECKLIST FOR FORMWORK
REQUIREMENT
|
|||||||||
Sr. No.
|
DESCRIPTION
|
REMARK /YES /NO
|
|
|
|
|
|
|
A
|
FORMWORK FACE TREATED WITH
SHUTTER RELEASE OIL
|
|
B
|
ALL THE PROPS ARE VERTICAL
|
|
C
|
PLATES SPANNED PERPENDICULAR
TO THEIR STIFFENERS
|
|
D
|
1st PROP FOR BEAM BOTTOM AT
230 mm FROM COLUMN FACE
|
|
E
|
BEAM BOTTOM PROPS SPACING
BETWEEN 60 Cm.
|
|
F
|
PROPS ABOVE 3 METERS ARE
BRACED.
|
|
G
|
ALL SLOPING CHAJJA PROPS
BRACED.
|
|
H
|
WEDGE SYSTEM IS USED FOR ALL
PROPS UNDER SLOPING SLAB
|
|
I
|
NO COLUMN FORMWORK
DESHUTTERED WITHIN 24 HOURS
|
|
|
|
|
J
|
NO SLAB SHUTEERING &
FORMWORK DESHUTTERED BEFORE
|
|
1
|
10 DAYS FOR SLABS SPANNING
UPTO 4.5 m
|
|
2
|
14 DAYS FOR SLABS SPANNING
OVER 4.5 m
|
|
|
|
|
K
|
NO BEAM SHUTEERING &
FORMWORK DESHUTTERED BEFORE
|
|
1
|
14 DAYS FOR BEAMS SPANNING
UPTO 4.5 m
|
|
2
|
21 DAYS FOR SLABS SPANNING
OVER 4.5 m
|
|
CHECKLIST FOR CURING TIME OF CONCRETE
COMPONENT
PERIOD
FOOTING 7 DAYS
COLUMN
14 DAYS
SLAB
14 DAYS
Sr. No.
|
DESCRIPTION
|
REMARK /YES /NO
|
|
|
|
|
|
|
A
|
CURING FOR FOOTING IS DONE
FOR 7 DAYS
|
|
B
|
CURING FOR COLUMN IS DONE
FOR 14 DAYS
|
|
C
|
CURING FOR SLAB IS DONE FOR
14 DAYS
|
|