CHECKLIST FOR FORMWORK REQUIREMENT & CHECKLIST FOR CURING TIME OF CONCRETE


CHECKLIST FOR FORMWORK REQUIREMENT
Sr. No.
DESCRIPTION
REMARK  /YES  /NO






A
FORMWORK FACE TREATED WITH SHUTTER RELEASE OIL

B
ALL THE PROPS ARE VERTICAL

C
PLATES SPANNED PERPENDICULAR TO THEIR STIFFENERS 

D
1st PROP FOR BEAM BOTTOM AT 230 mm FROM COLUMN FACE

E
BEAM BOTTOM PROPS SPACING BETWEEN 60 Cm.  

F
PROPS ABOVE 3 METERS ARE BRACED.

G
ALL SLOPING CHAJJA PROPS BRACED.

H
WEDGE SYSTEM IS USED FOR ALL PROPS UNDER SLOPING SLAB

I
NO COLUMN FORMWORK DESHUTTERED WITHIN 24 HOURS




J
NO SLAB SHUTEERING & FORMWORK DESHUTTERED BEFORE

1
10 DAYS FOR SLABS SPANNING UPTO 4.5 m

2
14 DAYS FOR SLABS SPANNING OVER 4.5 m




K
NO BEAM SHUTEERING & FORMWORK DESHUTTERED BEFORE

1
14 DAYS FOR BEAMS SPANNING UPTO 4.5 m

2
21 DAYS FOR SLABS SPANNING OVER 4.5 m




CHECKLIST  FOR CURING TIME OF CONCRETE
  
COMPONENT                              PERIOD                                                           
FOOTING                                           7    DAYS
COLUMN                                          14    DAYS
SLAB                                                  14    DAYS


Sr. No.
DESCRIPTION
REMARK  /YES  /NO






A
CURING FOR FOOTING IS DONE FOR 7 DAYS

B
CURING FOR COLUMN IS DONE FOR 14 DAYS

C
CURING FOR SLAB IS DONE FOR 14 DAYS