CHECKLIST FOR STORAGE OF CEMENT ON SITE & CHECKLIST FOR CEMENT IDENTIFICATION


CHECKLIST FOR STORAGE OF CEMENT ON SITE 

1) To stock 500 bags, godown size of 7 x 3 meters is found most suitable. Height should be 2.0 metres to 2.0 metres. 

2) The godown should have a high plinth so as to prevent ground water from entering. Stock cement on a platform and put plastic sheets below. 

3) Do not keep any windows or ventilators for the godown.

4) The godown should have two doors, so placed that cement can be stocked and removed on First come, First use basis.

5) The cement godown should be airtight, and should not be left open at any time.

6) Stack only 10 bags in a height.

7) Keep sufficient space between the stocked bags and the walls of the godown.



CHECKLIST FOR CEMENT IDENTIFICATION

a) Always check the manufacturing Week/Month/Year printed on a cement bag before unloading. The cement should be from the current week (or closest) so as to get the maximum strength from the cement used. Cement is found to loose strength with the age.

b) Weigh cement bags regularly. A tolerance limit of ± 1 Kg. is acceptable.

c) Check the following with respect to cement :
i) Date of manufacture
ii) Batch no.
iii) Ask for Cement Test Reports from the manufacturer. For this,                     Acron's Purchase Dept will help you to obtain it.