CHECKLIST FOR STRENGTH REQUIREMENTS FOR CONCRETE








a) MAINTAIN A WATER/ CEMENT RATIO OF 0.5, i.e. use 25 lts of water per bag of cement.

b) Testing of cube moulds of 150 x 150 x 150 mm


STRENGTHS IN Kg/cm2

Concrete

Grade

Target Strength of

150 mm cube at

3 days in Kg/cm2.

(60 % strength)

Target Strength of

150 mm cube at

7 days in Kg/cm2.

( 77 % strength)

Target Strength of

150 mm cube at

28 days in Kg/cm2.

( 100% strength)


M20

170

218

283


M25

200

256

333


STRENGTHS IN N/mm2

Concrete

Grade

Target Strength of

150 mm cube at

3 days in N/mm2.

(60 % strength)

Target Strength of

150 mm cube at

7 days in N/mm2.

( 77 % strength)

Target Strength of

150 mm cube at

28 days in N/mm2.

( 100% strength)


M20

17.0

21.8

28.3


M25

20.0

25.6

33.3


All the testing cubes should be cast from a single concrete mix batch. (load).


Concrete Strength

Ration of Nominal Mix

Theoretical Consumption per

Minimum Cement Content per cum.

Strength Required in Kg/ cm2 by


3 days

7 days

28 days


M20

1:1.5:3

8.20 bags

6.40 bags

170

218

283


M15

1:2:4

6.40 bags

6.00 bags

140

179

233


M10

1:3:6

4.40 bags

4.40 bags


M7.5

1:4:8

3.40 bags

3.40 bags


Note: Cement bags of 50 kg



Item of work

Type

Ratio of Mix

Theoretical consumption


Masonry

Laterite (All Sizes)

1:5

1.90 Bags / Cum


Masonry

Brick 230 thk. and above

1:5

1.46 Bags/ Cum


Masonry

Brick 115 thk. And below

1:5

1.46 Bags/ Cum


Masonry

Concrete Block 200 thk.

1:5

0.60 Bags/ Cum


Masonry

Concrete Block 150 thk.

1:5

0.60 Bags/ Cum


Masonry

Concrete Blocks 100 thk.

1:5

0.60 Bags/ Cum


Plaster for brick masonry

18mm thk. In double coat

1:3 & 1:4

0.255 Bags/ Sqm


--Do--

12mm thk in single coat

1:4

0.155 Bags/ Sqm


For ceilings

8mm thk in single coat

1:3

0.144 Bags/ Sqm


Plaster for Laterite Masonry

18mm thk. In double coat

1:3 & 1:4

0.311 Bags/ Sqm


-- Do--

12 mm thk. in single coat

1:4

0.188 Bags/ Sqm


Drip moulds/ band

Per cum of work

1:4

7.650 Bags/ Cum


Flooring

IPS 50mm thk. Incl. Plaster and neat cement slurry

1:2:4

0.450 Bags/ Sqm


Note: Cement bag of 50 kg.