Analysis of Rates
12 cm thick Cement plaster in
CM (1:4)
Unit 1 Sq.m
Take – 100 Sq.m.
Particulars
|
Qty. or Nos.
|
Rate
Rs. Rs.
|
Cost
Rs. Rs.
|
|
Materials
-
|
||||
Cement
– 12 bags
|
0.4
cum
|
2400.00
|
960.00
|
|
Sand –
1.6 Cum.
|
1.6
cum.
|
68.00
|
108.80
|
|
Labour etc. -
|
||||
Head mason (mistri)
|
1/3 No.
|
48.00
per day
|
16.00
|
|
Mason
|
10 Nos.
|
40.00
per day
|
400.00
|
|
Mazdoor including racking of
joints
|
13 Nos.
|
24.00
per day
|
360.00
|
|
Bhisti (including curing)
|
¾ Nos.
|
28.00
per day
|
21.00
|
|
Scaffolding, sundries T &
P etc.
|
Lump Sum
|
16.00
|
16.00
|
|
Total
|
813.00
|
|||
Total
of material and labour
|
1881.80
|
|||
Total of material &
labour
|
1881.80
|
|||
Add 1 ½ % water charges
|
28.20
|
|||
Add 10 % contractors profit
|
188.20
|
|||
Grand Total Rs.
|
2098.20
|
|||
Rate per Sqm (2098.20/100) =
Rs. 20.98 say Rs. 21
|
For 100 Sqm.
|
|||