Analysis of Rates
1st class brick
masonry in superstructure with 20 x 10 x 10 cm brick with 1:6 Cement Sand
Mortar – Unit 1 Cum.
Take 10 Cum
Particulars
|
Qty. or Nos.
|
Rate
Rs. Rs.
|
Cost
Rs. Rs.
|
Materials -
|
|||
Brick – 1st class
|
|||
500 bricks per Cum
|
5000 nos.
|
520.00
|
2600.00
|
Cement bags (13.5 bags)
|
0.45 cu,m,
|
Per 100
2400.00
Per cu.m.
|
1080.00
|
Sand (local)
|
2.7 cu.m.
|
68.00 per cu.m.
|
183.60
|
Total
|
3863.60
|
||
Labour etc. -
|
|||
Head Mason (Mistri)
|
½ Nos.
|
48.00 per day
|
24.00
|
Mason
|
10 Nos.
|
40.00 per day
|
400.00
|
Mazdoor (labour)
|
7 Nos.
|
24.00 per day
|
168.00
|
Male coolie
|
10 Nos.
|
16.00
per day
|
160.00
|
Bhisti
|
2 Nos.
|
28.00 per day
|
36.00
|
Scaffolding
|
Lump Sum
|
18.00 L.S.
|
18.00
|
Sundries, y & P, etc.
|
Lump Sum
|
8.00 L.S.
|
8.00
|
Total
|
834.00
|
||
Total
for materials & Labour
|
4497.60
|
||
Add 1
½ % water charges
|
60.45
|
||
Add 10
% Contractors Profit
|
469.75
|
||
Grand
total
|
5227.80
|
||
Rate per Cum = Rs. (5227.80)
/ 10
= Rs. 522.78 say Rs.
523.00
|