The following works are to be completed prior to commencing laying of Ultra Tiles.
· Final painting of ceiling in rooms.
· Two coats of wall painting in all rooms (the final painting should be done only after laying of floor tiles).
· Wiring and fixing of all electrical components.
· Plumbing work.
· Fixing of grills for windows.
· Fixing and polishing of windows / window frames / door frames and doors.
· Bathrooms floor and walls tiles should be laid after all the work in the bathroom are completed.
· Fixing of wall and platform slabs.
If Mosaic/Marble/any other natural stone which needs machining and polishing is being used in any other part of the floor, it is necessary that this work be completed before commencing the laying of Tiles.