Prepare
a list of activities included in a project, along with other depending
activities.
Prepare
a rough draft first.
Find
the estimated time required for completing each activity.
Write
down this estimate on each activity.
Prepare
scheduling computations and find the earliest and latest allowable start
and finish times for each activities so as to identify the critical path
and to indicate the amount of slack on non-critical paths.
Prepare
the final form to be used in the field. The project is to be controlled by
checking off progress against the schedule.