SHALIMAR GROUP | NAME OF THE DEPARTMENT : | DOCUMENT CODE NO. | |||||||||||||
EXECUTION | |||||||||||||||
NAME OF THE DOCUMENT : | PAGE NO. | TOTAL PAGES. | |||||||||||||
CHECKLIST FOR BRICK MASONARY (AFTER AND DURING BRICK MASONARY WORK ) | 0 | 1 | 0 | 1 | |||||||||||
CHECKLIST FOR BRICK MASONARY (AFTER AND DURING BRICK MASONARY WORK ) | |||||||||||||||
Sr. No: | |||||||||||||||
SITE : SHALIMAR ANTHURIUM | LOCATION : | DATE : | |||||||||||||
Ref. Drawing No. ________________________________________ | |||||||||||||||
Sr. No. | Job Description | YES | NO | NA | |||||||||||
CHECKLIST AFTER BRICK MASONARY | |||||||||||||||
1. | Check for curing arrangements? | ||||||||||||||
2. | Check for defects if any? | ||||||||||||||
3. | Check for rectification required? | ||||||||||||||
CHECKLIST FOR DURING BRICK MASONARY | |||||||||||||||
1. | Check whether dimensions are as per drawings? | ||||||||||||||
2. | Check for sizes of doors / window openings? | ||||||||||||||
3. | Check for margins left for plastering jambs? | ||||||||||||||
4. | Check for dry mixing on hard and clean surface before adding water to mix proportion of mortar? | ||||||||||||||
5. | Check for plumb / line / level | ||||||||||||||
6. | Check for cleaning area for dead mortar and brick bat to location of disposal? | ||||||||||||||
7. | Check for curing arrangements? | ||||||||||||||
8. | Check for racking of joints to receive plaster / pointing? (both sides of wall) | ||||||||||||||
SIGN. OF SITE ENGINEER | |||||||||||||||
CORRECTIVE ACTION PROPOSED | |||||||||||||||
Sign of Project Manager Sign of Project Manager Contractor Shalimar Group |