CHECKLIST FOR PIPING LAYOUT CONCEALED

0
1

0
1
CHECKLIST FOR PIPING LAYOUT CONCEALED

Sr. No:




SITE : SHALIMAR ANTHURIUM
LOCATION :
DATE :
Ref. Drawing No. ________________________________________
Sr. No.
Job Description
YES
NO
NA
1.
All supply points : ('O' of pipes, points to be in proper location with proper projection.



2.
Master stop-cock.



3.
Divertor.



4.
Spout



5.
Basin mixer-hot and cold



6.
Shower



7.
Heater-supply and delivery pipes.



8.
Washing m/c-supply.



9.
Washing m/c-drain.



10.
Flush



11.
Jet System.



12.
Plugging all open points of item



13.
Pressure testing of all pipes in item



14.
Test pressure (double the working head notless than 50 psi)




During Process



1.
Mortor mixed to proper ratio.



2.
No Bricks are used to fill gaps.



3.
Mortor filled to be in line level with plaster.



4.
Curing is done for 7 days.



5.
Expanded mortor 200mm wide to be fixed over plumbing pipe.



6.
All concealed pipes to be properly covered with bitumenious paints & hessian cloths.








                                                                                          

                                                                                          SIGN. OF SITE ENGINEER
CORRECTIVE ACTION PROPOSED



Sign of Project Manager                                                       Sign of Project Manager
      Contractor                                                                                  Shalimar Group