Stacking of concrete blocks

  • Fresh concrete blocks should be stored on the levelled ground/below parking area/below a covered area.

  • More than 6 blocks should not be stacked one over the other in a single column.

  • There should be a minimum of 5 cm gap between two rows. After every row of 25 blocks, there should be a discontinuation. This gap helps the curing water to reach upto the bottom of each column. It also allows circulation of air for drying in a uniform manner, upto the last block of each column.

  • For curing, date-wise lots of the blocks should be made. Curing should be done five times for a minimum of 15 days. Boards with the manufacturing date should also be displayed on the day’s lot.

  • Blocks should be stacked on a flat face for better stability.

  • As far as possible, stock and cure the blocks under covered portion so as to retain the moisture cement.



Stacking of Concrete Blocks



Stacking of Lime sanla powder

  • It should be stored on a raised platform approximately 15 cm to 20 cm above ground level.

  • Roofs and flooring should be waterproof to prevent contact with water.

  • It should be placed where it can be locked.

  • Minimum openings should be there.