Prepare analysis of rate for U.C.R. masonry in C.M. (1:6) Unit 10 Cu.m.



Material required
Dry rubble required : 12.5 m3 for 10 cu.m. to account for bond stones.
Wastage etc: Assuming 50% dry mortar requirement.

Cement required
= (5 m3/1+6) x 1
= 0.71 cu.m.
= 0.71 x 30
= 21.5 bags

Sand required
= 0.71 x 6
= 4.26 m3

Material cost:


Rubble
12.5 x 60/-
750 = 00
Cement
21.5 x 68/-
1462 = 00
Sand
4.26 x 25/-
106 = 50

                  Total
2318 = 50
Labour


Mistri (Head mason)
½ No. x 60/-
30 = 00
Mason
12 Nos. x 45/-
540 = 00
Mazdoor (Bedar)
10 Nos. x 18/-
180 = 00
Boy coolie
10 Nos. x 12/-
120 = 00
Bhishti
1½ Nos. x 18/-
27 = 00
Scaffolding
Lumpsum 30/-
30 = 00
Sundries, T and P etc.
Lumpsum 6/-
6 =00
                                                        Total
933 = 00

Total of material + labour = 3351.50

Add 1½” water charges     =     48.77

                                         Rs. = 3300.27


Add 10% of contractors profit i.e. 330.02

Total rate = Rs. 3630.30 per 10 m3


Therefor Rate per m3 = Rs. 363.03