Give the meaning of the following:

Extra item

Prime cost


Extra item:
While quoting a tender a list of items to be carried out by the contractor is quoted. During execution of the work however, an additional item of execution may arise or the quantity of work for a particular item mentioned in contract may increase above the decided in contract. In both cases, the ‘item’ is referred as extra item and additional charges are required to be paid to the contractor for its execution.

Prime cost:
While preparation of a detailed estimate for any work certain quantities like water supply – sanitary – door – electrical fittings cannot be exactly worked out as they are bound to fluctuation in accordance with the wishes of the owner. Hence, to account for such items a lump-sum amount expressed as some ‘percentage’ of the tendered cost for work is included while inviting a tender and is known as ‘prime cost’.


State the circumstances under which revised and supplementary estimates are prepared.

Revised estimate

Revised estimate is prepared under the following conditions:

When the original sanctioned estimate is exceeded by 5% or more.

The expenditure on a work exceeds or is likely to exceed by 10% on the original administrative sanction.

Fluctuations and deviations in materials with respect to quantity and costs from the original proposal.

During execution of work if it is noticed the original sanctioned estimate is over-excessive.


State the units of measurements of the following

Surface excavation

Door frame

R.C.C. slab 12 cm thick

Iron work in trusses

ITEMS
UNITS
Surface excavation
Cubic-meters
Door frame
Cubic-meters
R.C.C. slab 12 cm thick
Square-metres
Iron work in trusses
Quintal or tonnes.