Common Area Works
1.Staircase and Lift
wall to be constructed along with structure.
2. Block work for common area and shafts are completed.
3. Electrical conduiting and box fixing is completed.
4. Staircase wall and ceiling plastering is completed.
5. Lobby area plastering is done.
6. Staircase railing and lobby railings are fixed.
7. Staircase and common area flooring and dadoing (as per specification) are completed.
8. Granite coping and lift architraves granite works are completed.
9. Putty, sanding and first coat paint to ceiling are completed.
10. Services like Plumbing and fire are completed.
11. Electrical wiring works are completed.
12. Shaft door fixing is completed.
13. Shaft door painting is completed.
14. Grouting of floor tile, wall tile and granite are done.
15. Silicon sealant works are completed.
16. Signages are fixed.
17. Final snagging and handover of common area to CRM.