Terrace Works:Work Sequence of Building Construction


Terrace Works:

1. Up stand beam to be cast by providing provision for stub columns.

2. Concreting of stub columns.

3. Parapet block work completed.

4. Coping for the parapet wall done.

5. Structural works such as OHT, Staircase headroom, Lift machine room, flush tank, battery room etc.to be completed.

6. Block work to be completed for all the above mentioned service rooms.

7. Electrical conduiting & Box fixing works to be completed.

8. Ponding test to be done to check the water tightness of the terrace slab.

9. Tanks to be filled with water and water tightness to be checked.

10. Kurrah fixing (Outlet for draining rain water) to be completed with bore packing.

11. Bull strips are made.

12. Light weight screed is completed to slope.

13. Haunching to be done at the junction of all vertical and horizontal surfaces to enable smooth transition of waterproofing.

14. Waterproofing as per waterproofing calendar /Specifications issued to site.

15. Protective screed for the waterproofing done.

16. Plastering for all surfaces to be completed.

17. Plumbing bracket fixing work to be completed.

18. Terrace pipe line works to be completed.

19. Terrace flooring works to be completed.

20. Skirting works to be completed.

21. Miscellaneous works such as OHT ladder fixing, staircase handrail for lift machine room, door fixing for the rooms, painting works, fixing of solar panels & water heaters, lightning arrester, aviation lights etc. to be complete.

22. External painting to be completed.

23. Painting for all the MS works.

24. Expansion joint treatment to be completed (if any).

25. Non-shrink expansion joint material to be filled as the specification.

26. Snagging and hand over to CRM.