Terrace Works:
1. Up stand beam to be cast by providing provision for stub columns.
2. Concreting of stub columns.
3. Parapet block work completed.
4. Coping for the parapet wall done.
6. Block work to be completed for all the above mentioned service rooms.
8. Ponding test to be done to check the water tightness of the terrace
slab.
9. Tanks to be filled with water and water tightness to be checked.
10. Kurrah fixing (Outlet for draining rain water) to be completed with
bore packing.
11. Bull strips are made.
12. Light weight screed is completed to slope.
13. Haunching to be done at the junction of all vertical and horizontal
surfaces to enable smooth transition of waterproofing.
14. Waterproofing as per waterproofing calendar /Specifications issued
to site.
15. Protective screed for the waterproofing done.
16. Plastering for all surfaces to be completed.
17. Plumbing bracket fixing work to be completed.
18. Terrace pipe line works to be completed.
19. Terrace flooring works to be completed.
20. Skirting works to be completed.
21. Miscellaneous works such as OHT
ladder fixing, staircase handrail for lift machine room, door fixing for the
rooms, painting works, fixing of solar panels & water heaters, lightning
arrester, aviation lights etc. to be complete.
22. External painting to be completed.
23. Painting for all the MS works.
24. Expansion joint treatment to be completed (if any).
25. Non-shrink expansion joint material to be filled as the
specification.
26. Snagging and hand over to CRM.