Structure (start to finish) Work Sequence of Building Construction


Structure (start to finish) Work

1. The site boundary and marking pillars are marked and is cross checked with reference to the setting out drawing.

2. Receipt of approved current construction drawing for footing and excavation (Architectural & Structural) from Architects.

3. Checklists for all the activities to be filled and approval taken.

4. Mass excavation /manual excavation are started.

5.Anti termite treatment is done.

6. PCC for footing with soling (if required) to be done.

7. Marking for footing and columns.

8. Reinforcement for footing.

9. Shuttering/form work for footing.

10. Concreting for footing.

11. Pedestal marking and concreting.

12. Column marking / casting

13. Reinforcement/lapping.

14. Column box shuttering,

15. Column concreting

16. Meter marking/staircase columns.

17. Beam bottom marking/shuttering.

18. Shuttering for beam side / slab.

19. Leveling and QC/ Architects checking.

20. Reinforcement for beam, beam bottom, electrical conduiting, plumbing cutout and top mat.

21. Beam outer side shuttering.

22. Check by structural consultant /QC.

23. Pour card/batch ticket signature to be taken.

24. Concreting of slab/beam supervised under the PH (Staircase and Lift wall are cast along with the structure).

25. Cubes are cast as per Indian Standards.

26. Sprinkling of water to be started the moment concrete surface starts to dry.

27. Ponding / hessain cloth curing to be done for 7 days

28. Column starter marking for the next floor.

a. Repeat the procedure from point 12-27 for the next level.

29. De-shuttering started after achieving required strength as per IS requirements. (With temporary supports to beams/slabs).

30. Hacking to be done on concrete surfaces for plastering and slurry coat to be applied to concrete surface at junction of block workand concrete.

31. Marking course of block work is done and is checked by Quality Engineer.

32. Block work done using templates for doors and windows openings.

33. Meter marking is done on the block work with coloured line dori

34. Lintels/sills/chejjas are cast with reference to meter level.

35. Mesh fixing is done at the junction of block work and concrete and is packed with mortar.

36. Ceiling plastering is done. (PVC rings are provided for the electrical junction boxes).

37. Button marking for the wall plaster is done.

38. Electrical chasing, conduiting and box fixing including DB box fixing and packing are done.

39. Window grills and balcony railings are fixed.

40. Wall plastering is completed including the toilets. Meter marking is again done on the surface as explained earlier.

41. Plumbing chasing, pipe fixing in toilets/kitchen is completed and tested and packing is done

42. Electrical wiring is completed.

43. Fire sprinkler works are completed.

44. Main floor screed for tilling is completed.

45. Bore packing in toilets, balconies and utilities are completed.

46. Ponding test is done to check the water tightness of the bore.

47. Screeding for toilets, balconies and utilities are done.

48. Internal painting comprising of primer, 2 coats of putty for ceiling and wall is done.

49. Toilet and kitchen dadoing is completed. ( except for bottom line of tile)

50. The main flooring is completed and the tile surface is protected.

51. Under tile waterproofing is done for toilets, balconies and utilities.

52. Floor tilling for toilets and balconies are completed and protected.

52. Skirting for the main flooring is completed and the last tile dadoing is finished.

52. Window sill and balcony coping granite works are completed.

52. Sanding and first coat paint to ceiling and wall is completed.

53. False ceiling frame works and E-board works in balconies and utilities are completed.

56. Texture and first coat paint for balconies and utilities are done.

56. Aluminum windows, ventilators and doors are fixed.

57. SIL door frames and shutters are fixed.

58. Electrical switch plates are fixed.

59. Touch up putty and sanding to wall and ceiling are done.

60. False ceiling works in toilets are completed.

61. Grouting of wall and floor.

62. Final coat paint.

63. Plumbing fixtures are fixed.

64. Silicon sealant works are completed for toilet and kitchen areas.

65. Final snagging and handover of flat to CRM.(Refer Clearance Process from QST)