Lift Works:

1.Lift well waterproofing is completed.

2. Lift wall to be constructed along with structure.

3. Block work for the lift openings to be done as per manufacturer’s drawing.

4. Lintel to be cast with allowance for granite architrave.

5. Lift well block work plastering to be completed.

6. White washing to be done to the lift well.

7. Electrical conduiting is done; bulk heads and socket points are fixed.

8. Lift frame and door is fixed by vendor.

9. Granite frame and architrave are fixed.

10. After handover of lift from the agency, the lift flooring to be done.

11. Protection done for the walls and the ceiling of lift.

12. Final snagging and handover of Lift to CRM