Basement Work Sequence Of Building Construction


Basement Works:


1. Backfilling to be done in layers and compacted.

2. Soil profile to be graded as per the required slopes.

3. Anti-termite treatment to the soil is done.

4. Car wash drains and tanks to be constructed.

5. Soling is done to the required profile.

6. PCC is done.

7. All the high level services such as electrical, plumbing, fire are completed.

8. Lift lobby works are completed.

9. The services rooms such as panel rooms, telecom rooms, pump rooms, Water treatment plants,maintenance room etc… are completed.

10. VDF (Vacuum dewatered flooring) is completed.

11. Car wash drain covers are placed.

12. Ceiling painting (Tyrolene) to be completed.

13. Column and wall painting to be done.

14. Electrical light fittings and car wash lines are completed.

15. Car park numbering and marking to be completed.

16. The shaft openings are enclosed in the basement.

17. Column fenders are fixed.

18. Signages and letter boxes are to be fixed.

19. Final snagging and handover of basement to CRM