TYPE - 1
BBS CALCULATION
BOTTOM
|
TOP
|
STIRRUPS
|
||||
Left
|
Mid
|
Right
|
Left
|
Mid
|
Right
|
|
2 –
25 Ñ„ + 2- 20 Ñ„
|
2 –
25 Ñ„ + 2- 20 Ñ„
|
2 –
25 Ñ„ + 2- 20 Ñ„
|
2- 20
Ñ„
|
2- 20
Ñ„
|
2- 20
Ñ„
|
8 Ñ„ @
100, 150, 100 c/c
|
BOTTOM BAR
Development length = 50d
1st layer
25 Ñ„ = length of beam +
development length – bend
= 5000 + (50 x 25 x 2) – (2 x
25 x 1 x 2)
= 7400 mm
= 7.4 meter
For 2 nos. = 7.4 x 2 = 14.8
meter
2nd layer
20 Ñ„ = length of beam +
development length – bend
= 5000 + (50 x 20 x 2) – (2 x
20 x 1 x 2)
= 6920 mm
= 6.92 meter
For 2 nos. = 6.92 x 2 = 13.84
meter
TOP BAR
20 Ñ„ = same as 2nd
layer of bottom bar
= 13.84 meter
STIRRUPS
For zone – 1
L/3 = 5000/3 = 1666.67 mm
No. of stirrups = (Length /
Spacing) + 1
= (1666.67 / 100) + 1
= 17.7 say 18 nos.
Total no. of stirrups for zone
1 = 18 x 2 = 36 nos.
For zone – 2
No. of stirrups = (Length /
Spacing) - 1
= (1666.67 / 150) - 1
= 10 nos.
Therefor total = 36 + 1 = 46
nos.
Cutting length of stirrups
a= 300 – (2 x clear cover) – (2
x half of bar)
a= 300 – (2 x 30) – (2 x 4)
a= 232 mm
b= 600 – (2 x clear cover) – (2
x half of bar)
b= 600 – (2 x 30) – (2 x 4)
b= 532 mm
cutting length = (2 x a) + (2 x
b) + (2 x 10d) – (3 x d x 2) – (2d x 3)
= (2 x 232) + (2 x 532) + (2 x
10 x 8) – (3 x 8 x 2) – (2 x 8 x 3)
= 1592 mm
= 1.592 meter
For 46 stirrups = 1.592 x 46 =
73.23 meter
Note:
For bend
45 degree = 1d
90 degree = 2d
135 degree = 3d