To set out plan for a residential building

<
Theory

Setting out plan for a residential building in a preparation of center line diagram. Marking the width of excavation on the ground from the working drawing with the help of wooden pegs, nails, string, tape and lime powder.
Application
Setting out plan for a residential building is very important as it is not possible to start the work to excavation for the foundation without setting a plan, if we start the work without setting a plan not be in a proper diamensions.


Items required

1.      Tape

2.    String

3.    Nails

4.    Wooden pegs

5.     Lime powder


Procedure

First step is to clear the site from all types of debris and organic materials. After clearing the disturbance, the proper scale should be selected for setting out residential building. Outer boundaries of building is fixed with help of wooden batten and center line plan. The building face is checked by right angle method with help of string. Generally rectangle should be checked by diagonals. Rectangle should be marked by 3,4,5 or 9,12,15. The centre line pegs are marked and fixed the width of foundation is marked with the help of plumb bob and lime powder.


Diagram






Precaution

1.   The diagonals should be equal for a rectangles and also be equal to its calculate value.

2.   Lines should be marked with the help of lime powder by stretching the sting tightly.


3.    Rectangle should be marked by 3,4,5 or 9,12,15 method accurately.