Estimating and Costing
Model Questions
Unit 5
1. A Simply Supported Beam 230mm x 300mm size of 4m clear span is reinforced with 3 bars of 20mm dia. Stirrups with 8mm dia. are provided at 200mm c/c. Calculate quantity of steel. Draw the sketch showing details of steel reinforcement. Assume missing data.
2. A Cantilever Beam of 230mm x 450mm size of 2m clear span is reinforced with 4 bars of 16mm dia. Stirrups with 8mm dia. are provided at 200mm c/c. Calculate quantity of steel. Draw the sketch showing details of steel reinforcement. Assume missing data.
3. A One-way slab for a room of 3m x 7m size is provided with 120mm thick slab. Main Steel Reinforcement is 8mm dia. at 150mm c/c. Find Steel Required. Assume Missing Data.
4. A RCC Square Column of 300mm x 450mm size of 3m height above plinth beam is reinforced with 4 bars of 20mm dia. Lateral ties with 8mm dia. are provided at 200mm c/c. Calculate quantity of steel? Assume depth of foundation below Plinth beam is 2m. Draw the sketch showing details of steel reinforcement
Unit 6
1. Explain: a) Security Deposit b) Arbitration
2. Explain various types of Tenders?
3. Explain various types of Contracts?
4. Explain about Tender Notice?
Unit 7
1. Explain various methods of Valuation of Buildings?
2. Explain necessity of Valuation?
3. Explain various methods of calculation of depreciation?
4. Explain factors affecting Valuation of Property?
Unit 8
1. Give the detailed specifications of the following items of works.
a. (a) Painting (b) Flooring
2. Give the detailed specifications of the following items of works.
a. (a) PCC (1:4:8) (b) Brickwork with 1st Class Bricks
3. List and explain standard specifications of a first class building?
4. Give the detailed specifications of the following items of works.
a. (a) RR Masonry (b) Plastering