Activities
|
1.0- Project Management System
|
With reference to Contract Documents determine the following
|
Identify the processes needed for the quality management system
|
Determine the sequence and interaction of these processes,
|
Determine criteria and methods needed to ensure that both the
operation and control of these processes are effective,
|
Ensure the availability of resources and information necessary to
support the operation and monitoring of these processes,
|
Monitor, measure and analyze proejct management
processes
|
Implement actions necessary to achieve planned results and continual
improvement of these processes.
|
Integrate contractual requirements into Project Management System
|
Developed PQP with reference to Contract Documents
|
Comply with ISO 9001:2000 Requirements
|
Systems implementation and maintenance
|
Develop Contract Management Procedure In coordination with Proejct
Manager – Commercial Manager – Engineering Manager
|
with respect to the following:
|
a) Inspection & Testing
|
b) Materials submittals & approvals
|
c) Eng. shop-drawings & approval
|
d) Progress reproting
|
e) Design change change control
|
f) Variations & claims management
|
g) Monthly payment certificates
|
h) Forms / records and numbering system
|
Estbalish Project Information & Communication Management
System
|
2.0- Project Organization
|
Ensure Organization Structure approved and issued to Project Team
|
Issue approved Departmental Functions to relevant departments
|
Issue Job responsibilities to Project Team
|
Submit Responsibilities and authority matrix for approval by SR
Projects Manager
|
3.0- Project Records
|
Apply MAR Standard forms as a baseline
|
Review Contract Documents and make a list of Contract Specific Records
required
|
Review & Approve Forms in coordination with Consultant
|
All forms to have an ID No and cross-referenced with
relevant SOPs or ITPs
|
Define, list and maintain all quality records required by Project
Management System and Contract Requirements
|
Develop Project Information Flow Plan – Distribution Matrix
|
4.0- Document & Data Control
|
Establish Project file index system
|
Documents and Submittal reference numbering system
|
Project Distribution Matrix
|
Establish Project Logs for:
|
Materials Submittals – Documents submittal – Drawings Submittals
|
Request for Information – Variation orders – Inspection request –
Materials inspection
|
Approve documents for adequacy prior to issue,
|
Review and update as necessary and re-approve documents,
|
Ensure that changes and the current revision status of documents are
identified,
|
Ensure that relevant versions of applicable documents are available
at points of use,
|
Ensure that documents remain legible and readily identifiable,
|
Ensure that documents of external origin are identified and their
distribution controlled
|
Prevent the unintended use of obsolete documents, and to apply
suitable identification to them if they are retained for any purpose
|
Control of Incoming and outgoing correspondence
|
Control of incoming and outgoing documents
|
5.0- System Review
|
Analysis of Results of internal and external audits
|
Customer feedback
|
Process performance and product conformity – Analysis of Records
|
Status of preventive and corrective actions,
|
Follow-up actions from previous management reviews,
|
Changes that could affect the quality management system, and
|
Recommendations for improvement.
|
6.0- Inspection & Test System
Development
|
List of required ITPs and scheduled of preparation – This should be in
Line with List of Method Statements
|
Review contract specification for tolerances and MAReptance criteria
of the activities
|
Identify and agree with the Consultant on Suppliers / Subcontractors
Sources Inspection & Testing
|
Prepare relevant ITP using MAR FM-E01
|
The ITP shall describe the following:
|
a) Activity description.
|
b) Responsibility.
|
c) Reference to Technical Specification clauses.
|
d) Reference to relevant codes / standards.
|
e) Inspection / test requirements and frequency .
|
f) Inspection category (Hold, Notification, Surveillance, Record
review).
|
g) MAReptance criteria as per the project specification and/or
applicable codes and standards.
|
h) Make reference to supporting documentation (Inspection
records Reports/…etc.)
|
Submit ITP to the Consultant for approval
|
Once approved issue as a controlled to relevant sections
|
7.0- Inspection & Test System Implementation
|
Ensure ITP submitted by Section / Site Eng.as per daily schedule for
inspection
|
The Section Eng. to verify that Surveying and MEP activities are
checked and validated
|
Register details of WITR in the WITR Register FM – E03 and
allocate Ref No
|
Inspect the work and verify completeness and compliance in MARordance
with MAReptance criteria
|
If the work can be submitted to Consultant for Final approval – Invite
the Consultant – If the work can not be submitted, request the section Eng to
carry out the required remedial works
|
Perform a joint Inspection with the Consultant and sign- off the WITR
if the work is MARepted by the Consultant
|
Inform the Section Eng with the results of the inspection for
proceeding with the works or carry out remedial works as deemed required
|
Follow – up with Section Eng. to ensure required actions / remedial
works completed.
|
Maintain quality records specified by the ITP
|
Perform Statistical Analysis on test results to ensure complaince with
MAReptance criteria
|
8.0- Pre-Construction
|
Coordinate with Construction Manager to esnure the following
activities are completed
|
Issue of Approved Construction Schedule
|
Issue of Approved Method statement
|
Issue Approved Shop – Drawings
|
Issue Approved ITPs
|
Materials delivered are inspected and verified
|
Verify that the Construction Manager has completed FM – D35 – Activity
pre- start Check list
|
Appointment of relevant subcontractor and required submittals are and
approved
|
Follow – up Minutes of Meeting from Sub-contractors Kick-off meeting –
Ensure Quality Documents submitted on time
|
9.0- Engineering Management
|
Coordinate with Engineering Manager with respect to the following
issues
|
Shop drawing Submittal Schedule is approved and distributed
|
Materials submittal schedule is approved and distributed
|
QA Review of Materials submittal including subcontractros
|
QA Review of Engineering Documents Submittal – NOTE the PQM is not
responsible for the technical details of the shop-drwaings
|
Submittals status monitoring and control on weekly basis
|
Montior implementation and compliance with Engineering SOP
|
10.0- Procurement Management
|
Coordinate with Materials Engineer with respect to the following
issues
|
Suppliers / Subcontractors Selection & Evaluation –
Prequalification
|
Suppliers / Subcontractors Performance Measurement
|
Monitoring status of submittals
|
QA Review of submittals made by Subcontractors
|
Montior implementation and compliance with Procurement SOP
|
11.0- Construction Management
|
Coordinate with Proejct Manager / Construction Manager with respect to
the following issues
|
Review Method statement for complaince with Contract Documents
|
Ensure the use of Activity pre – start planning checklist by
Construction Team – Ensure activity input requirements are in place
|
Monitor implementation / compliance with Mehtod Statement
|
Routine Inspection of Works
|
Scheduled inspection of works – In MARordance with relevant ITPs
|
Handling and processing work inspection request
|
Verification of setting out lines and levels – Check with the surveyor
|
Trend Analysis of Construction progress delays and request for
Corrective and preventive actions
|
Coordination with consultant on all issues related to Quality Control
|
Deviations from specification must be supported by a record in the
form of Engineering Concession
|
Control of Non-conforming Product
|
Corrective and preventive actions
|
Montior implementation and compliance with Construction SOP
|
12.0- Materials Control
|
Prepare Materials Test plan – Define form the specification test
required on materials and make of Field Materials Testing ITP
|
Identify Materials and test required to be carried out by Independent
Laboratory
|
Receiving Inspection & Testing of Materials
|
Inspection / Testing of materials / products at source prior to
delivery as deemed required.
|
Control of Non – conforming Materials
|
Corrective & Preventive actions
|
Traceability Control
|
Maintenance of Records
|
13.0- Site Audits
|
Carry out Audits as per Audit Schedule
|
Analyze Audit findings and feedback to Management Review Process
|
Follow – up on Corrective Actions & timely closure
|
Performance Measurement as part of the Audit
|
14.0- Project close out
|
Testing & Commissioning Activities to be Completed as per
scheduled dates
|
As Built- drawings
|
Snagging
|
Operation & Maintenance Manuals for Equipment & Systems
|
Manuals for Materials & finishes
|
Training of Facility Engineering, Operating & Maintenance
Personnel
|